|
Brookwood Baptist Church, Shreveport
| Owner:
Brookwood Baptist Church, Shreveport
Contractor: Lincoln
Builders Inc., Ruston
Cost: $6.8 million
Architect: SGB Architects,
Shreveport
|
In seeking a solution to its lack of space for future growth
at its 30-year-old Shreveport facility, Brookwood Baptist
Church knew relocation would be a major factor in solving
the space problem.
To continue their vision of meeting the ministry needs of
their community, the congregation selected a site at the intersection
of Interstate 49 and Bert Kouns Avenue, an area showing growth
and promise for expansion.
A key issue in relocating the campus was selecting a method
of construction that would best utilize the congregation's
financial investment through construction cost savings, low
maintenance and reduced operating costs.
After thorough comparison of conventional structural steel/masonry
construction, pre-engineering metal building and concrete
tilt-wall construction, the building committee accepted the
architect's recommendation to incorporate tilt-wall construction
into the design.
The Tilt-up Concrete Association (TCA) reports that in Texas
and other Sunbelt states, tilt-up accounts for as much as
75 percent of new one-story commercial building construction,
yet the process is underutilized in the religious construction
market.
As contractor of choice for the 58,000-sq.-ft. facility,
Lincoln Builders Inc. of Ruston embarked on the project in
September 2002 to provide Brookwood Baptist with the advantages
tilt-wall construction could afford, such as construction
cost savings, fast construction schedule, safety and aesthetics.
Wood framing was assembled on the floor slab to form a mold
for the 36-ft. panels, providing exact shape and size, doorways
and window openings to meet the design specifications and
fit together properly. With the network of reinforcing steel
bars tied into the form, workers installed inserts and embeds
for lifting the panels and attaching them to the footings,
roof system and to each other.
The slab beneath the forms was then cleaned of debris and
water, and concrete was poured into the forms to create the
panels.
Once the concrete panels solidified, the forms were removed
and the panels were connected to a 124-ton crane with cables
that hook into the inserts. The 25,000-lb. panels were lifted,
or "tilted" up, by the crane into a vertical position
above the footings where workers guided and set them into
place.
The process was repeated to form and erect 160 panels, reaching
completion of the building shell within three months and saving
six months construction time over conventional construction.
|