|
ExxonMobil Aromatics 2400 Volt Substation
Replacement Project
| Owner:
ExxonMobil Chemical, Baton Rouge
Contractor: Industrial
Specialty Contractors, Baton Rouge
Cost: $275,000
|
In September 2003, ExxonMobil Chemical requested lump sum
bids through ExxonMobil Chemical for electrical and instrumentation
work to upgrade an aging substation serving the critical aromatics
unit at its Baton Rouge facility. The bid package specified
that a new 2400-volt substation was to be installed in the
same location - an extremely congested area containing numerous
high-voltage feeders.
ExxonMobil Chemical awarded Industrial Specialty Contractors
LLC a lump-sum contract valued at $275,000 for all labor,
supervision, equipment and materials. The project scope included
all electrical and civil work necessary to replace the substation,
modify the foundation and feeders, install power control systems
and then test and cut over the new system with minimal interruptions
in plant operations.
ISC was also responsible for scheduling, pre-check and review
of the testing and commissioning procedures.
The project was organized in five phases. The first phase
involved installation of temporary power for two 480-volt
switch racks and two 2,400-volt motor starters. Pre-substation
electrical and civil work was completed in phase two, which
included disconnection and removal of power and control wiring.
Also in phase two, two 3,750 KVA transformers with neutral
ground resisters and foundations were removed and the existing
foundation was modified to accept the new substation.
The old substation was demolished and removed in phase three.
During phase four, ISC associates installed the new substation
and two 2,400-volt transformers, two 5,000 KVA transformers,
new HVAC/pressurization equipment and three new air conditioning
units. Terminations, final power and control connections were
completed in phase five, along with testing, commissioning
and substation start-up.
|