|
Children's Hospital ER/OR, New Orleans
Contractor:
Brice Building Co. Inc., New Orleans
Cost: $17 million
Project manager: Pat Descant
Assistant project manager: Mitch
Melancon
Jobsite superintendent:
J. T. Livaccari
Architect: Eskew+Dumez+Ripple,
New Orleans |
The team of architect Eskew+Dumez+Ripple and contractor Brice
Building Co. Inc., both of New Orleans, integrated form and
function during construction of the Children's Hospital Emergency
Room and Operating Room.
From the multi-colored floors with triangles, circles, and
squares intricately mingled into the patterns to the rich
maple hardwood registration desks, the design intent of the
hospital is clear - provide a visually rich environment that
soothes visitors and appeals to the children with its abundant
use of color.
Design and construction goals combined with maintaining a
fully functional hospital led to some innovation and extremely
close coordination among hospital staff, design team and contractor
personnel.
The contract documents contained a very detailed, precise
phasing plan that had to be strictly adhered to in order to
maintain hospital operations. At several points during construction,
Brice Building Co. discussed alternate phasing options with
the hospital in order to maintain functionality and also facilitate
construction operations.
In addition to providing the owner with the full cooperation
of subcontractors during discussions involving tie-ins and
unforeseen conflicts, Brice was able to value engineer nearly
a $236,000 credit that was shared between the owner and contractor.
Also, due to the very limited construction staging areas,
working relationships between field supervisory personnel
and hospital staff had to be strongly established.
During steel erection, access was routed differently almost
on a daily basis in order to ensure safety for visitors and
pedestrians entering the hospital. At one point, spotters
were used to temporarily halt erection while pedestrians entered
and exited the building.
Also, field supervisory personnel worked closely with hospital
staff to ensure that speedy mobilizations and demobilizations
were executed to accommodate an already limited parking availability.
With nearly 180,000 visitors entering the doors annually,
a majority of the work was hinged around maintaining access
to the emergency room and MRI for the duration of the project.
In addition, countless tie-ins had to be made to the central
plant's mechanical, electrical and control systems. These
tie-ins had to be coordinated with the hospital on a daily
basis to prevent interference with critical hospital operational
systems.
Tropical storms Lili and Isabel struck at the most inopportune
times and, despite a few unavoidable small leaks, no considerable
damage was done and hospital life care systems were never
once compromised. Several times during the pile driving operations,
Brice was directed to shut down due to open-heart surgery
only feet away, in existing surgery suites. Several shutdowns
were scheduled after hours and work was scheduled in the middle
of the night in order to perform critical medical gas tie-ins.
Hundreds of steel beams weighing tons were delicately lifted
above the existing emergency room wing and MRI to erect the
new structure. Electrical systems had to be tied into existing
systems with minimal effect on non-construction areas. Fire
ratings and emergency egress had to be maintained at all times
during construction, while at the same time not hindering
access to the non-construction areas of the hospital.
|