|
SM1 Modernization Project, ChevronPhillips
Chemical, St. James
Contractor:
Performance Contractors Inc., Baton Rouge
Cost: $41 million
Project executive: Brent
Boe
Jobsite superintendent:
Laurey Coupel
Engineer: Bechtel Corp.,
Houston, Texas |
Chevron Phillips' SM1 project was a culmination of successes
generated through focus and purpose prior to the project going
to the field, which in turn supported Performance Contractor
Inc.'s ability to achieve all predetermined goals of execution.
The most notable accomplishment of the SM1 project was the
ability of Performance Contractors to expend 550,000 direct
manhours and incur no OSHA recordable injuries.
The construction phase of the SM1 project took place within
the existing, operating styrene facility at the plant. Performance
expended 375,000 direct manhours during this phase, which
was highlighted by the installation of 600 tons of structural
steel, 2,133 spools of fabricated pipe and the placement of
the 914-ton recycle column.
Clear communication between Performance and ChevronPhillips'
plant operation was a constant activity throughout this phase
of the project. The existing styrene monomer unit had no plant
shutdowns as a result of construction activities during the
16-month schedule.
Performance Contractors had peak manpower of 300 during
construction, combined with 75 subcontractors, which made
the overall site extremely congested.
The recycle column constituted the highest level of challenge
for Performance Contractors and the SM1 project. ChevronPhillips'
project management made the decision to have the column fabricated
in India prior to awarding the general contract to Performance.
Upon award of the contract, the contractor was responsible
for the shipment of the column from India to the plant site,
offloading and transporting into the facility, and erection.
Trips to visually inspect work in India was hindered due to
the Sept. 11, 2001, terrorist attacks.
Performance management, along with the transportation and
crane subcontractor, met in Amsterdam with the Indian fabricator
to review work progress and shipment plans. The column is
256 ft. tall and 28 ft. in diameter.
|