|
Battle stations
Fort Polk course cleared,
contoured for digital battle area
By Martin W. Schwartz
A training ground 5 mi. south of Kisatchie in the Kisatchie
National Forest is shaping up to become one of only a handful
in the country.
Tug Hill Construction, which is based in Felt Mills, N.Y.,
is sculpting Fort Polk's Digital Multi-purpose Battle Area
Course (DMPBAC) out of 6,000 acres of Louisiana countryside.
Polyengineering Inc. of Dothan, Ala., designed the course
for the U. S. Army Corps of Engineers.
Tug Hill recently completed a similar training facility in
Fort Knox, Ky. The contractor was awarded the contract for
the Fort Polk project in September 2003 and site clearing
began March 26.
Then the rains came.
"Locally, we had three times the average rainfall,"
said James R. Didas, jobsite superintendent with Tug Hill.
"I think we worked 12 days out of 24 in June." Working
overtime has allowed the crew to make up for lost time, with
earthmoving operations nearly 75 percent complete in September.
The first step in the $29.2 million battle course was to
clear 1,100 acres and trim 2,300 acres of the Kisatchie National
Forest needed for the project. Fort Polk, located about 20
mi. from the training area, maintains 60,000 acres in the
forest for its use.
A 20-mi. road was paved through the 6,000 acres that will
ultimately make up the training ground.
When completed, the course will be a state-of-the-art training
facility for the Army's "Stryker," a 19-ton wheeled
armored vehicle capable of sustained speeds of 60 mph that
can be deployed by C-130 aircraft and be combat ready upon
arrival. The 2nd Armored Cavalry Regiment of Fort Polk is
one of six Interim Brigade Combat Teams to use the new vehicle.
Because the Stryker will be shooting at targets up to a mile
away, line of sight is imperative to the construction of the
training course.
"They have given firing points and what's called a 'firing
matrix' that designates which targets they can see from which
locations," Didas said.
These special requirements mean that some hillsides must
be "shaved" away and flat areas raised. As a result,
more than 1.25 million yds. of ground have been moved at the
site by as many as 12 tractors and pans.
Didas equated the earthmoving to "sculpting" the
topography to create realistic simulations of a variety of
terrains. All of the excavated earth was utilized in other
areas of the jobsite.
Erosion control at the jobsite has also been significant,
said Kate Mangan, project manager for Tug Hill. About 15,000
timbers were delivered to the site from companies in Texas
and Mississippi to be used in retaining walls.
"Piles are driven into the ground and the timbers were
stacked behind them and backfilled with dirt," Mangan
said. "This created raised areas with earth and berm
on one side and the electronically controlled target on the
other." The downrange area includes 10 moving infantry
targets, 215 stationary infantry targets, moving armor targets,
50 stationary armor targets, 11 battle positions and 10 machine-gun
bunkers.
The project also requires crushed rock tank trails; a service
road; installation of several low water crossings; installation
of primary electric, hard-wired camera towers; fiber-optic
communication system; septic fields sewage lagoon connection;
and installation of water lines, storm drainage systems and
a number of permanent sediment ponds.
Didas said the low water crossings are unique.
"They've got large arch pipes in the design," he
added. "Five are designed for water overtopping the structure.
Water will actually build up a bigger flow than the pipe can
handle and the water will go over the top of the road."
JCF Bridge and Concrete of Austin, Texas, provided the steel
pipes in sizes from 12 to 32 ft. in diameter.
"They're basically large culvert pipes," Didas
said. "We're doing the excavation. The fabrication and
installation are being done by JCF."
A cutting-edge computerized control center is also being
constructed so the Army can control troop movements on several
fronts and send information in real time to one central command.
"They can train on this range and train on the range
in Kentucky and send all the information to the control building
at Fort Hood (in Texas)," Didas said. "The person
sitting at Fort Hood can control and command the operations
in all three locations."
To achieve that level of technology, about 258,000 lin. ft.
of fiber-optic cables will be run throughout the course.
"Some of those cables have more than 100 fibers in them,
so there's a tremendous amount of fiber optics involved,"
Didas said.
Dean Rypkema, project manager for Nelcorp of Endicott, N.Y.,
which is performing the fiber-optic and electrical installations,
said the installation of the fiber optics is similar to those
done on other military ranges.
"We'll dig deep trenches, drop it in the ground and
cover it up," Rypkema said. "We don't expect anything
different than what we've done before. It's just a big 6,000-acre
playground." Installation is scheduled to begin in early
to mid-November.
Telephone communications require 25,000 ft. of copper wire,
and 228,000 lineal ft. of high voltage cable will be needed
for power.
Other subcontractors include American Forest Products of
Anococo, clearing contractor; Camo Contractors of Vidalia,
earthwork contractor; and Westerchil Construction of Alexandria,
building subcontractor.
Didas said strict requirements and guidelines, particularly
in the safety area, must be followed for the government project.
The corps has its own health and safety manual, and Tug Hill
had to write its own health and safety plan before work could
begin.
"Anyone who wants to go onsite has to go through safety
indoctrination," Didas added.
Because the site incorporates an existing live-fire range,
Tug Hill has to coordinate around scheduled exercises.
"It's not like they're shooting at us or doing anything,
but part of the range falls in their safety buffer,"
Didas said. "We have to stay behind a certain line, which
on this job is called the 480 line (an Army coordinate gridline)."
Since the area is being used as a tank training range, the
ground is being cleared by Tennessee-based EOD Technologies
to remove any live ordinance that might have remained on the
grounds.
"They go through and do a surface sweep to remove the
unexploded ordinance prior to us performing work," Didas
said.
He added that there are currently 75 workers onsite and the
project should be completed on schedule by next fall.
Useful Source:
For additional info on initiatives at Fort Polk, go to: http://www.jrtc-polk.army.mil/
|