|
Hurried hotel
Vinton complex dashes toward
December completion
By Karla Wall
Despite a hot and rainy Gulf Coast summer, construction of
a $26.5 million hotel and event center at Delta Downs Racetrack
and Casino in Vinton should be completed in late December.
Adverse weather conditions are nothing new for Yates Construction
of Philadelphia, Miss., which has built and renovated several
casinos along the coast and is accustomed to heat and rain.
"It's important for us to communicate daily," said
project manager Stephen Harrell. "We have to maintain
communication and coordination with the subcontractors to
make sure they know what's expected of them."
The fast-tracked project requires a 24/7 schedule, with two
10-hour or three eight-hour shifts and 200 workers, representing
about 12 subcontractors. Separate superintendents oversee
each shift.
Timely material deliveries are also important in such a fast-paced
construction environment, Harrell said. Numerous truckloads
of concrete block, precast and ready-mix concrete and steel
are delivered to the site daily. To ensure safe delivery of
materials, existing topsoils were replaced with compactable
fill to accommodate heavy machinery and delivery trucks.
The current phase, which began construction in mid-April,
requires construction of a new 10-floor hotel, food court
and event center. The first two phases of the project, begun
in September 2003 and finished this summer, involved renovations
to the interior of the existing casino area, the addition
of gaming space, a player's club area, a promenade, new buffet
area and glass-and-steel entrance to the gaming area.
Included in the first two phases were the repositioning of
the escalators and the re-designing of the HVAC and lighting
systems in the gaming area. The main entrance to the casino
was also moved and the cargo road entrance was refurbished.
With so many employees working in the high-stress environment
of a fast-tracked project amid heavy-duty machinery and delivery
vehicles, safety is paramount, Harrell said.
"We want to be sure that the men and women who say goodbye
to their families in the morning go home to say hello to them
in the evening," he added.
To that end, all fill dirt is leveled at the site to ensure
stability of cranes, constant communication is maintained
between machinery operators and workers, and the site is tidied
up each evening to ensure a safe site for the next shift.
When the hotel and event center project broke ground, a small
amount of site clearing was followed by the placement of clay
silt hauled from a borrow pit in Vinton. Precast concrete
piles were then driven to a depth of 73 ft.
After pile caps were constructed, columns were formed and
poured-in-place to support the second through ninth floors
and a penthouse level.
"The first two floor levels were built using structural
steel reinforcement and about 3,400 cu. yds. of 4,000-psi,
poured-in-place concrete," Harrell said. "Floors
on the third through 10th levels were constructed with 4-ft.-wide
precast hollow-core concrete planks anchored to block walls
with structural steel and concrete fill."
The hollow-core slabs measure 12 to 16 in. thick, said Jerry
Duncan, field manager with supplier CoreSlab of Oklahoma City.
More than 200 truckloads of the rectangular slabs will be
delivered to the site by the project's finish.
"The slabs are poured and tensioned at our manufacturing
facility in Georgia," Duncan said. "The planks are
arranged in a horizontal position, grouted and filled to create
a continuous slab."
About 4,300 cu. yds. of concrete will be used for the total
project, said Dan Correll with civil contractor Wright Construction
of Memphis. The contractor is utilizing a Versa-Form shoring
system to form the walls, while the structural deck is formed
with plywood.
The exterior walls of the hotel tower will consist of metal
studs, interior finish materials, insulation and an Exterior
Finish Insulation System.
The project's electrical system involves a challenging vertical
rise installation, said Yates project engineer Tony Bourgeois.
"We had to 'rough in' the wiring while at the same time
constructing the structural walls and floor assemblies so
that the active 'hot' electrical service work could be performed
on the floors below," Bourgeois said.
Chillers for the HVAC system will be installed at grade,
with piping routed below grade to designated mechanical rooms.
The four-pipe system will consist of an air-cooled chiller
system with hydraulic heating, said Reggie Barnes, project
manager with Mechanical Construction Co. of New Orleans.
"The main chiller will be located along with the boiler
plant adjacent to the main tower of the hotel complex, with
cooling and heating water routed underground to the facility,"
Barnes said. Vertical fan-coil units will be installed in
each room.
MCC is also responsible for installing the plumbing system
in the new complex, as well as four domestic water heaters
with hot-water return systems. The heaters will be located
on the first floor and will serve the hotel's low-rise and
tower.
The event center will consist of a 14,400-sq.-ft. pre-engineered
metal building manufactured by NuCor of Terrell, Texas, and
installed by H & H Metal of Sulphur. The building, constructed
of 24-gauge metal walls, will be delivered to the site and
erected this month, said H & H estimator Mike Leger.
The building will be delivered to the site using about six
trucks and will be erected by crane and bolted together or
welded on-site, Leger added.
Harrell said the key to the successful completion of such
a fast-paced, high-tension project involving so many subcontractors
at once is planning and coordination.
"Everything is planned meticulously months before the
work even begins," he added. "Schedules are pre-established
and are built on common production practices.
"We've built this project many times over on paper and
in our minds before work ever starts."
Useful Source:
For more information about Delta Downs' expansion plans,
go to: http://www.deltadowns.com/site/newscasino/detail.cfm?ID=14
|