|
Mixing it up
Ivan Smith warehouse uses
multiple concrete applications to make up for lost time
By Martin W. Schwartz
When the Ivan Smith Furniture Co. began building its new
warehouse on Shreveport's west side, there wasn't a lot of
discussion about what to use in the building's construction.
"I believe there is an ordinance in the Shreve Industrial
Park (in which the new warehouse is located) that all facilities
be made of tilt-wall construction," said Christopher
T. Sitton, project manager/estimator for Brown Builders Inc.
The Bossier City firm is responsible for building the 100,000-sq.-ft.,
$7 million warehouse project.
"This is a design-build project, meaning that Brown
Builders has utilized its own architects and engineers to
try to meet the owner's needs," he added.
Located nearly 10 miles west of its current warehouse, the
new Ivan Smith Furniture facility will operate 24 hours a
day as the receiving, storage and distribution center for
the retailer. With 30-plus stores currently serving the three-state
area known in north Louisiana simply as the Ark-La-Tex, the
Ivan Smith Furniture warehouse has been designed to meet the
company's current needs while allowing for future expansion.
"They've got a total of 17 acres and we're currently
working on only 8 to 10 acres," Sitton said. "They've
definitely planned for their future."
The north wall of the structure was designed to be non-load
bearing, allowing one, two or all the panels to be easily
removed to accommodate growth.
Groundbreaking on the warehouse took place in February with
underground, utility and associated work paving the way for
a scheduled slab placement on Memorial Day weekend.
But then the rains hit, and Sitton said spring rains and
a huge volume of concrete created problems during the project.
June storms pushed slab placement back six weeks. "We
have tried to look for specific areas where we know we can
step up our schedule," he said. "We're putting in
better than 10-hour days and six-day weeks."
Initial slab placement was to be carried out in 10 days time
but was completed in seven. That's no small feat because the
finished slab carried ultra stringent flatness specifications
to ensure that 40-ft. furniture storage racks and the telescoping
retrieval equipment have a secure and level base.
Builders Supply of Shreveport provided the concrete, and
it worked with Ace Avant Concrete Construction of Archdale,
N.C., to develop a new mix design.
"What we used was the design that was preferred by (Ace
Avant), a mix design they had used on past projects and had
good results as far as flatness, finish ability and overall
performance of the concrete," Sitton said.
Judd Wagler, a sales representative for Builders Supply,
wouldn't disclose the exact composition of the mix design
but said that local aggregates were used.
The first placement of 750 cu. yds. of concrete was completed
between the hours of midnight and 8 a. m. and was tested immediately
upon curing by Face Consultants, a Kentucky-based company.
Ace Avant and Face Consultants were the only businesses outside
of the Shreveport/Bossier area used in the project.
Sitton said that after nearly 100,000 sq. ft. of concrete
was tested, only two areas of approximately 1 sq. ft. each
were out of tolerance and required additional grinding.
The slab is pulling double duty by serving as the casting
bed for the warehouse's new walls. Two layers of bond breaker
were spread over the slab to ensure little or no damage to
either the floor or the wall panels.
"One layer is more than likely suitable, but at the
cost per pound we're looking at, it's a preventative measure
to assure that the panel will not stick to the slab,"
Sitton said. "It's pennies on the dollar compared to
what it would cost to break the panel off the slab."
Forms were constructed on the slab with window and door openings
in place. Nearly 2,500 cu. yds. of concrete will be used in
the creation of the 9.25-in.-thick wall panels, which are
formed as near to the point of erection as possible. The shortest
panel will be 35 ft. and the tallest approximately 45 ft.
in height.
A portion of each panel will be below grade in order to tie
into the structural drill shafts - 20-ft.-deep holes sunk
into the ground around the structure, filled with concrete
and topped with a welding plate. The parking lot will be cast
up to the erected panel and the finished floor will tie into
the wall panel as well, locking it between two concrete pours.
Each panel has 10 to 15 weld plates and the overall project
has nearly 800 weld plates to hold the concrete walls in place
and provide structural integrity.
Trio Fabricators of Shreveport will be responsible for lifting
and placing each panel as it is completed with a 200-ton crawler
crane. While the heaviest panel weighs 60,000 lbs., the company
is preparing for twice that weight to initially break the
seal of the concrete panel off the slab.
Once in place, the concrete will be sandblasted, textured
and painted.
"We will have reveals associated with windows and openings
to try to form some kind of architectural feature other than
looking at just plain ugly concrete," Sitton said. He
pointed to the Frymaster building just west of the site as
an example of an aesthetically pleasing tilt-wall structure.
He added that the most unique aspect of the project was the
sheer volume of concrete required for the job.
"I think we placed 80 to 100 cu. yds. of concrete an
hour during the initial placement," Sitton said. "That's
eight to 10 trucks an hour."
When the project is finished, including site paving, curving
gutters and other necessary work, Sitton said the warehouse
will require more than 5,000 cu. yds. of concrete and will
have been visited by more than 200 concrete trucks.
The Ivan Smith Furniture Warehouse is currently scheduled
for completion by mid-December, but Sitton said Brown Builders
is working steadily to improve on that date.
"This is one of those jobs that the start date may have
drug out a little, but our completion date has remained the
same," he added.
Useful Resource
For more information about tilt-up concrete construction,
go to: http://www.tilt-up.org/
|