|
Fortifying Tiger Stadium
New concrete upper deck to
be taller, wider
By Sam Barnes
Working on the most watched jobsite in Louisiana has its
perks.
"We don't have to work most Saturdays in the fall,"
said construction manager Mark Houck with Yates Construction
of Philadelphia, Miss. The contractor is in the middle of
a $60 million project that will replace LSU Tiger Stadium's
west upper deck with a wider and taller concrete structure
with about 500 new seats, a club level and state-of-the-art
press box.
About 20,000 cu. yds. of high-strength, 6,000-psi concrete
will be placed for the new deck.
To prevent a reduction in seating capacity during the current
football season, none of the demolition will occur until after
the last home game on Nov. 26. Crews are instead constructing
foundations, four poured-in-place concrete elevator shafts
and a new pedestrian ramp at the south end zone.
"This is a high profile project with some time-sensitive
issues," said Jim McArthur, Yates' business development
manager. "We ramped up to get construction up to a certain
level, then geared down during the football season."
An existing parking lot on the west side is being used as
a laydown yard.
Any week preceding a home game concludes with an intensive
effort to fan-proof the site and allow access to all major
entrances to the stadium. The contractor also fences off the
site perimeter.
Yates began work at the site in January with a test pile
program by Gulf South Piling & Construction of Jefferson.
"We re-designed the pile configurations and lengthened
the piles to 114.5 ft," Houck said. Most of the nearly
700 piles will support new elevator shafts, the pedestrian
ramp and deck support columns.
"The majority were precast concrete piles, but we had
some 16-in.-diameter steel pipe piles in areas where we had
overhead obstructions within the existing stadium," he
added. The pipe piles were driven in 20-ft. segments, then
welded together to reach the specified length.
Construction began this summer on the four new west side
elevator shafts, two at the north and south corners and two
in the middle. Each shaft is more than 145 ft. tall and about
280 sq. ft. Anywhere from 74 to 89 piles were driven for each
shaft.
"In an effort to get as much done as possible, we slip-formed
the north elevator tower all the way to its final elevation,
while the remaining shafts only go part of the way up with
conventional forms," Houck said. "They won't be
finished until after demolition."
High-strength concrete supplied by Angelle Concrete of Baton
Rouge is being placed for much of the job, with some 5,000
psi mix placed for the foundations. About 90 percent of the
concrete will be pumped by Concrete Eaters of Sulphur and
about 1,900 tons of reinforcing steel supplied by Southern
States Steel of Beaumont, Texas.
The largest foundation measures 105 ft. by 38.5 ft. by 8
ft. thick and will support the new south pedestrian ramp.
"The foundation for the ramp requires a little more
than 1,200 cu. yds. of concrete and was finished in September,"
he added. The ramp will take fans on the stadium's south end
from ground level to the upper deck.
Two weeks prior to the last game, Deep South Crane of Baton
Rouge will deliver a 1,500-ton lattice boom crane to the site
on 56 trucks in preparation for the demolition of the mammoth
upper deck.
"The crane will have 330 ft. of main boom and will
be assembled in the laydown area," Houck said. A 300-ton
crawler crane will assist with the demolition.
Louisiana Chemical Dismantling of Baton Rouge will perform
the demolition by cutting and removing large sections of the
upper deck. The largest single pieces to be removed - the
concrete raker beams that support the seating areas - will
weigh from 250,000 to 400,000 lbs.
"The men will be up there physically cutting these
sections out and burning the weld joints with torches,"
Houck said.
Once on the ground, the pieces will be reduced in sized
and hauled for crushing and recycling.
The demolition crew will begin at the south end of the site
and "work its way north, and we'll follow behind with
construction," Houck added.
Ralph Stogner, project manager with the Tiger Athletic Foundation,
the project owner, said removal of the upper deck should take
about 60 days.
"After the top comes off, the column configuration
will change somewhat," Stogner said. Existing columns
beneath the deck will be removed and new rectangular columns
will be built atop new transfer girders that measure 6 ft.
wide and 13 ft. deep.
"From the ground up, there will be 20 new columns,"
he added.
After the new poured-in-place raker beams are built, Boykin
Bros. Inc./Louisiana Concrete Products of Baton Rouge will
supply precast seat sections on a "just in time"
basis.
"We expect to be forming and pouring raker beams and
placing precast as early as the first part of March (beginning
at the south end)," Houck said.
At about the same time, Yates and its subcontractors should
peak at about 250 workers onsite.
Upon completion, the new deck, designed by Trahan Architects
of Baton Rouge, will extend further southward by about 100
ft. and will reach about 20 ft. higher.
"The majority of work will be finished before the 2005
football season, but final completion will follow in the summer
of 2006," Houck said. "While the seating will be
ready, we'll still be working on interior finishes, paint
and fixtures."
Useful Source:
For a live shot of the LSU Tiger Stadium project, go to:
http://www.lsusports.net/ad/sportlink.cfm?pagecode=ad-webcam#
|