|
Elbowroom
Chalmette refinery erects
hydrotreater unit on half-acre site
By Sam Barnes
Installation of a $95 million hydrotreater unit at a small
Chalmette refinery has been much more than a small task.
The unit will enable the 89-year-old refinery, owned by
Chalmette Refining LLC, to comply with an Environmental Protection
Agency requirement to lower the sulfur content in gasoline.
Chalmette Refining is a joint venture between ExxonMobil and
Venezuela's state oil company, Petroleos de Venezuela.
Within the unit, ExxonMobil Research and Engineering Co.'s
SCANfining gasoline sulfur reduction process will selectively
remove sulfur while minimizing octane loss.
Before the project is completed this fall, construction manager
Kellogg, Brown & Root of Houston and its subcontractors
must contend with a constricted half-acre jobsite and a diminutive
staging area.
"The most difficult design task, initially, was finding
enough real estate for the unit," said Joseph Kazda,
project execution leader with Chalmette Refining. "We
had to find a way to minimize the size of the unit to squeeze
it into the existing space, while complying with distance
requirements for the facility."
Engineers determined that three buildings and a nitrogen
plant on the perimeter of the plant could be demolished to
create the half-acre space necessary to support the unit.
"An existing warehouse within the refinery was transformed
into office space so personnel could be relocated from the
buildings," Kazda added.
While the project team is fortunate to have a jobsite on
the outskirts of the plant with its own dedicated entrance,
the site's small footprint leaves little area for material
laydown and prep.
"When subcontractors such as James Construction Group
of New Orleans or Harmony Corp. of Baton Rouge need to bring
in heavy equipment or lay a vessel down, there isn't a lot
of extra space to go around," Kazda said. To remedy the
problem, KBR leased laydown yards near the refinery for its
subcontractors.
Tom Jensen, KBR's senior project manager, said the project's
challenges have also been alleviated by KBR's ability to utilize
"best practices" from previous projects.
"KBR completed three similar projects for ExxonMobil
last year," Jensen added. "Because of that we've
been able to utilize their lessons learned, roll over some
of the people from those projects and do whatever we could
to benefit from those experiences."
He said the result has been less "re-work" in the
field.
To connect the new unit with the existing plant, Harmony
Corp. and Meraux-based Lou-Con performed 134 tie-ins as part
of the offsite phase of the project.
"We reinforced existing piperacks with new foundations
and steel to support additional pipe and brought the connections
up to the battery limits of the new unit," said Lester
Barback, vice president of construction for Harmony Corp.
Extensive planning was necessary to ensure Harmony's work
did not interfere with existing refinery operations.
"Our schedule required that certain sections be done
by certain dates," Barback added. "We had to turn
them over when the refinery needed them. There wasn't any
flexibility."
The offsite work was finished in mid summer.
"Our strategy was to get the offsite work finished
early so that everything would be confined to the jobsite
battery limits," said Troy Carter III, operations representative
with Chalmette Refining. "That helped us control the
schedule better."
Work within the new unit began in Spring 2003 when Professional
Construction Services of New Orleans excavated the site.
"When you have a site with a small footprint and a
lot of foundations, you don't want to have to dig down for
each individual foundation," said Conrad Bourg, Industrial
Division manager for James Construction Group. "It makes
more sense to 'bathtub' the entire site, then build foundations
and backfill." About 7,000 cu. yds. of fill material
was needed for backfill.
It was difficult to locate underground obstructions during
the excavation, given the age of the refinery.
"We used hydro-trenching to dig a trench around the
perimeter of the site with high pressure water," Jensen
said. "We identified how many lines were there and how
many of those actually matched to the drawings."
After removal of existing pipes and excavation, Berkel &
Co. of Bonner Springs, Kan., drilled 600 55-ft.-deep positive
displacement auger piles. James Construction Group then began
installing high-density polyethylene and carbon steel pipe
and building concrete slab foundations.
Bourg said the most complicated foundations included some
3-ft.-deep concrete slabs and two elevated tabletop foundations
for the unit reactors. There also was a large sump on the
southwest corner of the site to deal with.
"Ultimately, we placed about 3,300 cu. yds. of concrete
for foundations and site paving and installed about 5,000
ft. of pipe," Bourg said.
Harmony and Nichols Construction Corp. of Baton Rouge began
installing vessels and equipment within the hydrotreater unit
after most of James Construction's work and the unit's main
pipe rack by Group Contractors of Baton Rouge had been completed.
"That helped us stay out of each other's way, since
about 250 workers were working out here at peak," Barback
added. Having the entire site paved also minimized the impact
of inclement weather on the Harmony crew.
A furnace stack was the tallest piece of equipment to be
erected within the unit and was delivered to the site in two
sections, then welded, lifted and placed.
When space allowed, other columns and vessels were placed
on the ground so that piping, insulation and electrical and
instrumentation work - by ISC of Baton Rouge -
could be performed prior to erection.
Many of the heavy lifts were performed on weekends because
of lighter equipment traffic and fewer people working within
the refinery.
"We expect to finish the project in September, then
begin unit start-up in October," Carter said. "That's
the deadline we established in the beginning and so far we're
still on that schedule." About 400,000 labor hours will
have been worked by project's end.
Useful Source:
For more information on ExxonMobil's SCANfining technology,
go to: http://www.prod.exxonmobil.com/refiningtechnologies/fuels/mn_scanfining.html
|