|
Growing an interstate
Contractor appeases locals
while expanding Sulphur interchange
By Sam Barnes
Just how a heavily used interchange in Sulphur would remain
open was uncertain when its $19.6 million expansion began
in July 2003.
A proposal calling for the temporary shutdown of the LA 27
interchange was unacceptable to local businesses, so Gilbert
Southern Construction of Ft. Worth, Texas, used "constructability"
to find a solution.
The Gilbert Southern project team chose to build temporary
on and off ramps to appease the locals.
"By doing that, the ramps could remain open during the
project," said project manager Dan DeKaye said. "We're
in the middle of building the final ramps now." The final
ramps have been edged outward because of the roadway's wider
swath.
Temporary east- and westbound driving lanes were also built
along the entire 1.5-mi. jobsite so four lanes of traffic
could be maintained.
"We built detours along the outside lanes, then kicked
traffic out to begin constructing the center of the new interchange
bridge and to demolish the roadway leading to the interchange,"
DeKaye said.
Ultimately, the project in Calcasieu Parish will expand I-10
at the LA 27 interchange from four to six lanes and merge
two bridges into one. The project requires the complete removal
of the existing bridge followed by the construction of a more
functional five-ramp concrete interchange.
Construction of the bridge began with a significant foundation
phase performed during the wettest spring and summer on record
for southwest Louisiana.
"The abutments and columns are built on caissons that
are about 65 ft. long and 6 to 8 ft. diameter," DeKaye
said. W. W. Foundation Drilling Ltd. of Houston is performing
the foundation work.
Concrete columns, girders and a poured-in-place deck will
follow the caissons, with girders supplied by Gulf Coast Prestress
of Pass Christian, Miss., and ready-mix concrete supplied
by Dunham Price of Westlake. The longest bridge span reaches
140 ft.
After the inside bridge lanes were finished, traffic was
moved onto the new lanes so that the existing east and westbound
bridge spans could be demolished and reconstructed.
Heavy steel beams were removed and the bridges were "taken
down to their foundations," said project manager Pat
Cline.
"Switching from steel to concrete beams has made the
bridge about 3 to 4 ft. taller, simply because concrete beams
are taller than steel," Cline added. Other interchange
work requires construction of three block retaining walls
along the bridge and ramp embankments.
A new six-lane interstate both east and west of the bridge
is also being constructed and was preceded by a significant
earthmoving phase to create new road embankment.
"About 120,000 cu. yds. of embankment was placed, some
of which to accommodate the higher grade of the new bridge,"
DeKaye said.
In one location, a drop in road elevation was required to
provide clearance beneath an existing overhead pedestrian
bridge in close proximity to the interchange.
"The east side of the job has an arched pedestrian bridge,
and there's a 3- to 5-ft. cut to go beneath it," DeKaye
added.
As of July, the Gilbert Southern crew was about 70 percent
complete with the earthmoving.
After the embankment is in place, the Gilbert Southern crew
will rebuild the road with a cement-treated subgrade, 8 in.
of crushed concrete and limestone, and 12 in. of concrete
paving for the driving surface. About 31,000 tons of concrete
is being demolished from the existing roadway and re-used
in the new road base, and 50,000 cu. yds. of concrete is being
placed for the driving surface.
DeKaye said the expansion project should be finished by
the end of the year.
"We're currently on track to finish by the end of December,"
he added. About 70 to 80 crewmen are working at the site.
A soon-to-be-awarded project to the west will further the
six-laning of I-10 from LA 27 to Coone Gully. The project
was originally bid in June, but the lowest bid of $49.2 million
by Gilbert Southern was higher than the Department of Transportation
and Development's original estimate.
The project, to re-bid this month, will require grading,
subgrade treatment, lime treatment, in-place stabilized base
course, asphalt milling and a Superpave asphalt driving surface.
Construction should begin by late fall.
Useful Source:
For an update on the progress of the LA 27 project, go to:
http://www.dotd.state.la.us/construction/charles.html#CALCASIEU
|