|
Strength in numbers
Procter & Gamble liquid
detergent plant attracts 'cluster' companies
By Sam Barnes
Procter & Gamble's decision to build a second U.S. liquid
detergent plant at its existing dry detergent plant in Pineville
has yielded some notable fringe benefits.
Using Louisiana Economic Development's business clustering
model, P&G has attracted several front-end suppliers to
property adjacent to the $120 million plant. Plastipak Packaging
Inc., Calvary Industries Inc. and Integrated Packaging Corp.
are already building facilities at or near the plant.
"We're creating a supply chain here that more than justifies
P&G's investment," Plant Leader Todd Hoffman said.
"It's our objective to exceed the company's expectations
and we're on track to do that."
LED spearheaded the clustering concept as a remedy to the
downturn in the industrial/manufacturing sector. The concept
typically includes an anchor tenant surrounded by a group
of its suppliers.
"The best current example is P&G," said Mike
Taylor, director of Petrochemical Refining & Environmental
Technology Cluster Development for LED. "To manufacture
detergent you need bottles, so the bottle manufacturer is
locating across the street. You need a company to pre-blend
the materials, so that company is also locating nearby.
"The closer they get to the anchor tenant the better
all of their economies and bottom lines are, and the more
globally competitive they become," Taylor added.
To encourage clustering, LED uses the state's general fund
to finance projects that enhance infrastructure around potential
sites, including sewer, water and road improvements.
As a result, Pineville's infrastructure will get a boost
from the project.
"Our initial concern was water treatment," Hoffman
said. "The local plant was at capacity and we needed
to expand that. The second need was the road infrastructure
around the perimeter of the plant."
Long-range community demands for infrastructure have also
been addressed.
"We're not the only business out here, so future water
needs such as fire protection for area businesses were addressed,"
Hoffman said. Pineville also received a state grant to build
a wastewater treatment plant, necessary in part to accommodate
the P&G expansion.
Once infrastructure concerns were resolved, the new detergent
plant broke ground in early 2003. Fru-Con Construction Corp.
of Ballwin, Mo., is the project's construction manager, Inland
Construction of Pineville is the general contractor and Lockwood-Greene
Engineers of Spartanburg, S.C., is the engineer.
Jim Sexton, lead construction manager for P&G, said
the company's decision to build the new plant next to an existing
dry detergent plant was unprecedented.
"P&G has never built a liquids plant next to an
existing dry detergent plant," Sexton said. "That
means we're making and shipping product at the same time that
we're building."
At peak in September, about 800 construction workers will
be working next to hundreds of P&G employees.
"We've had a lot of constructability meetings to make
this work, because we're not only tying into existing buildings
we're building inside of them," Sexton said.
Contractors performed some of the preliminary work off site
to reduce the jobsite population.
"There's a lot of modular construction where our pipes
come in already placed in the steel, already heat traced and
insulated," Sexton said. "That enabled us to take
about 200 people off site, versus stick-building." Performance
Contractors of Baton Rouge performed most of the modular construction.
P&G also restricted access to the site's south road
"to allow construction deliveries to get in and out more
easily," Sexton added.
When work began in early 2003, replacing the existing clay
soil was the project team's immediate concern. The soil was
highly expansive and required a significant amount of cut
and fill.
Crews followed with more than 30,000 cu. yds. of concrete
for vessel and tank foundations.
"The tank farms had the largest continuous concrete
pours that P&G has ever had placed," Sexton said.
Beginning at night, Boh Bros. Construction of New Orleans
placed the concrete in 1,400- and 1,800-cu.-yd. pours. The
concrete was supplied by TXI's Alexandria plant.
"We started at 2 a.m., poured until about 5 p.m. and
finished at 10 p.m.," Sexton said. A special admixture
was added to the tank foundation concrete to reduce shrinkage
and cracking.
In other concrete work, The Haskell Co. of Jacksonville,
Fla., is building a final product warehouse with tilt-up concrete
panels using ready-mix supplied by Heck Industries of Baton
Rouge.
Lafayette Steel Erectors is assembling structural steel
for piperacks, tank and vessel supports.
"Most of the major vessels were fabricated offsite,
but those that were too large to transport were fabricated
and assembled at the jobsite," Sexton said.
Crews also retrofitted an existing warehouse to accommodate
the liquid plant's product differentiation and packaging area.
The original structure did not have adequate foundation or
structure to support an equipment mezzanine in the warehouse.
"We essentially took the roof off and took the columns
down, then Boh Bros. came back with new 4- to 5-ft.-diameter
caissons down to 28 ft. deep," Sexton said.
The new plant should begin producing new liquid detergent
by February 2005, although total completion is not expected
until next summer.
"After February, we'll complete areas of the plant that
are not critical to production," Sexton said.
Nearby, Plastipak Packaging's 500,000-sq.-ft. plant - the
largest cluster plant surrounding P&G - will be located
on 62 acres.
The plant will supply P&G with containers for the new
liquids production and will employ more than 100 employees.
A number of milestone technologies will be utilized at the
facility, including Plastipak's proprietary high-output, blow-molding
production system.
"We'll be linked electronically to Plastipak,"
said P&G public affairs coordinator Bonnie Lemoine. "If
we need bottles they'll know it."
The Calvary complex will supply liquid raw material to the
plant through a pipeline and Integrated Packaging will supply
corrugated material from a location within nearby England
Air Park.
"We're on schedule," Lemoine said. "We wish
we hadn't been hit with the wettest June on record for this
area, but we've managed to stay on track in spite of that."
Useful Source:
For more information about the new Plastipak plant, go to:
http://www.plastipak.com/news/08-12-03.html
|