|
Treacherous crossing
Suspected military ammo delays
Shreveport bridge project
By Sam Barnes
Just one span had been removed when the Louisiana Department
of Transportation and Development halted the $5.1 million
bridge replacement project over 12-Mile Bayou in Shreveport.
Rumors were circulating that unexploded World War II ammunition
was lurking in the Shreveport bayou, so contractor Blount
Bros. Construction of Shreveport had to move crews to other
projects while divers scoured the bayou bottom.
But after nine months of searching they had found only 155
empty mortar shells.
"They presumably had been left there by a nearby military
base," said Gene Ferguson, Blount Bros. jobsite superintendent.
When construction resumed in the fall of 2003, Ferguson had
to re-evaluate his schedule and "speed things up a bit
to make up some of the lost time."
Ultimately, an existing 28-ft.-wide, 500-ft.-long bridge
will be replaced with a 42-ft-wide, 720-ft.-long steel and
concrete bridge. Much of the extra width comes from the addition
of shoulders that will make the roadway safer and more accommodating
to increased traffic flow.
The bridge crosses beneath Interstate 220, which is a bypass
around the city.
Pharr Bros. Construction of Blanchard removed the existing
steel and concrete bridge in about four weeks.
"They tore it down with backhoes and removed the steel
girders from the shoreline with a 240-ton crane (operated
by Joyce Crane of Longview, Texas)," Ferguson said.
Demolished girders ranged from 20 to 64 ft. long and weighed
about 200 tons, and were hauled to a nearby scrap yard.
"The concrete was sent to our crusher to be broken down
into road base material," Ferguson said.
In December, Case Atlantic Co. of Clearwater, Fla., began
drilling eight 78-in.-diameter, two 60-in.-diameter and 33
36-in.-diameter auger shafts as foundation for the bridge's
superstructure.
Greg Wall, the project's engineer with the Department of
Transportation and Development, said only four of the shafts
were drilled in the bayou.
"Those were necessary to support the bridge's longest
spans, measuring 180 ft. and 130 ft.," Wall added. The
remaining two spans measure 115 ft. long.
To drill in the water, the Case Atlantic crew drove steel
casings through the bayou bottom, inserted augers through
the casings and drilled to depths of 110 ft. with the help
of a land-based crane.
"They drilled through a mud slurry," Wall said.
"As they pumped the concrete they took the slurry out
and put it in a holding tank. They re-used the slurry for
each shaft." TXI of Shreveport supplied Class S underwater
concrete during the foundation construction that contained
an additive to slow setting time.
"That allowed more time for reinforcing steel to be
inserted into the casing," he added.
Each shaft was poured 4 ft. above the water line and topped
with a single bridge column. The drilled shafts were completed
in about three months.
"We were fortunate to get the substructure finished
without having to deal with high water," he said.
The largest columns, located in the middle of the bayou,
measure 66 in. diameter and 20 ft. 6 in. tall and the smallest
columns at the bridge abutments measure 30 in. diameter and
1 ft. tall.
Using a Symons re-usable form system, the crew then formed
and poured column caps measuring 7 ft. wide by 4 ft. deep
with about 950 cu. yds. of concrete, all pumped from the shoreline.
Ferguson said the bridge's most striking feature will be
its large steel girders, which reach as long as 130 ft. and
as deep as 6 ft. 4 in.
"It's a bit unusual to have girders of this size. Directly
overhead is the I-220 bridge and its girders are not nearly
as big," he said, adding that the steel was necessary
to support the lengthy spans.
"Steel placement was performed by our crews early this
year with a 100-ton crane and 65-ton, barge-mounted tailing
rig," Ferguson said. The steel was fabricated by Afco
Steel of Little Rock, Ark.
"Afco delivered all of the steel in 'just in time'
fashion, since we had virtually no laydown area," Ferguson
said.
After the steel was placed, PAC Unlimited Inc. of Choudrant
installed metal pans as support for the bridge decking, which
was topped with an 8.5-in.-thick layer of concrete for the
driving surface.
"We used pump trucks with 140 ft. of reach from both
sides of the bayou during the pouring of the deck concrete,"
Ferguson said.
The remainder of the bridge is made of 11 20-ft.-long flat
deck bridge sections poured directly on top of the bridge
caps without precast girders. All of the concrete contains
reinforcing steel tied by Johnny Horton Contracting of Shreveport.
The bridge will be finished after PAC slip forms the concrete
barrier rail on both sides of the bridge.
In other work, about 1,300 ft. of roadway is being reconstructed
on the east and west sides of the bayou. The two-lane road
sections will accommodate the new bridge's higher gradation
and will have 10-ft. shoulders.
"On the south side we're shifting it to the west to
take out some of the curves," Ferguson said. "The
north side will be widened with new shoulders and ditches."
The reconstruction began in August when Blount Bros. removed
the existing asphalt roadway down to the base, then came back
with new soil embankment, 12 in. of soil cement and 4 in.
of asphalt driving surface.
"We expect to finish the entire project by mid September,"
Ferguson said.
Useful Source:
For an update on the progress of the project, go to: http://www.dotd.state.la.us/construction/shreveport.html#CADDO
|