|
Cookie cutter
Oschner tower gets expansion
sooner than expected
By Sam Barnes
Even though Ochsner Clinic's Critical Care Tower was built
in the late 1990s with future expansions in mind, Bill Ward
didn't expect to see an expansion in his lifetime.
Ward, Ochsner's vice president of facilities development,
had no idea that a dramatic increase in patient load at the
campus would mandate an expansion just three years later using
the same general contractor and many of the same subcontractors.
The new $16.4 million project is doubling the size of the
tower to seven floors and will be completed next summer. Brice
Building Co. Inc. of Metairie is building the addition, which
will add about 100 patient rooms.
Brice project manager Steve Judd said Ochsner's engineering
staff performed much of the design of the 3.5-floor addition
because the floors are "carbon copies" of each other.
"Each floor has 34 general purpose patient rooms and
a core space for a nurse's station," Judd added.
By using its own design staff, Ocshner will experience a
5 to 7 percent cost savings, as well as provide the owner
with more project control. Some "supplemental work"
was subcontracted to Rozas-Ward Architects of New Orleans.
The original 3.5-floor tower project was finished in 2000
and has a foundation and structure capable of supporting 11
floors, including large structural steel columns, enhanced
mechanical systems and a strong deep foundation system of
precast piles.
But Ocshner's Ward said he thought decades would pass before
future floors would be built.
"In fact, there is already talk about designing the
remaining four floors of the tower," he added.
Brice's current job is to build out the remaining half of
the tower's fourth floor, which will serve as mechanical space,
and build floors five through seven.
In August much of the design had not been completed, so the
structural package was released to allow the contractor to
begin construction.
"The steel was going up but we didn't actually get the
rest of the construction documents until later," Judd
said.
Erecting the steel proved cumbersome because of a limited
laydown area created by the streets and other campus buildings
that tightly border the site.
"We're working on top of an existing building in a tight
space and there's no laydown area," said jobsite superintendent
Don Plaisance. The hospital allows Brice to use a small alleyway
for delivery trucks so that steel and other materials can
be lifted and placed directly from the truck.
FabArc Steel of Oxford, Ala., fabricated 850 tons of steel
for the addition and Lafayette Steel Erectors used a 300-ton
crane to erect the steel. The crane was supported by a 40-
by 40-ft. concrete pad.
"When we bid the steel package, we asked for turnkey
numbers from the fabricators, including both fabrication and
erection," Judd said. "We wanted enhanced interaction
between the fabricator and erector."
One critical part of the steel phase was ensuring that the
columns "sat directly on top of each other" when
tying the new steel to the existing steel beams, since Ocshner
did not allow Brice to use of steel base plates.
"On a typical job, a base plate gives you some flexibility
because you don't have to be as exact when connecting the
beams," Judd said. "But this building is designed
to go up even higher, so you have to think long-term with
the overall design. You need to have the steel beams lined
up perfectly to maintain structural integrity."
Brice crews field-verified the steel coordinates "to
ensure that the steel being delivered to the site would be
dead-on," he added. After completion of the project,
the steel beams will stick about 3 ft. above the roofline
to allow for connections during the next expansion.
All of the addition's elevated slabs are made of composite
decks with sheet metal and 7.25-in.-thick concrete slabs reinforced
with wire mesh. Lafarge of Metairie supplied more than 2,150
cu. yds. of 3,000 psi pumped-in-place concrete for the project.
The semi-lightweight mix contained super-plasticizer to improve
pumpability.
Other work required a significant mechanical phase highlighted
by the installation of new air handling units in the fourth
floor mechanical room.
"We'll ultimately tie in to the existing Oschner mechanical
and electrical services," Judd said. A campus-wide mechanical
upgrade will eventually add chillers.
The building will also connect to the existing hospital via
an existing elevator tower.
Once the addition is complete in December, its exterior will
blend with the existing campus and include brick and precast
concrete bands, as well as glass and glazing.
"Rush Masonry of New Orleans is performing all of the
masonry work," Judd added.
Additional parking will be provided by the expansion of an
existing parking garage elsewhere on campus. That project,
which is not part of Brice's contract, is currently in the
pile driving stage.
Throughout its project, Brice has been required to coordinate
every phase with existing hospital staff. If a road closure
is necessary the hospital has to be notified two weeks in
advance.
That Brice and many of its subcontractors worked on the original
tower helped move the project along.
"Throughout the job, we've had some wrinkles thrown
at us and we're fortunate to have the original team from the
original job," Judd added. "It has really helped
smooth things out."
Useful Source:
For more information about Ochsner Clinic in Jefferson, go
to: http://www.ochsner.org/
|