|
Building an institution
Lafayette's new college campus
rises among live oaks
By Sam Barnes
Kendall Broussard, The Lemoine Co. Inc.'s project manager,
wasn't worried about demolition at the groundbreaking of Lafayette's
$12.5 million South Louisiana Community College last summer.
Only a few chicken coops had to be removed from the 5-acre
site.
But then there was the grove of centuries-old live oak trees.
"We were told by the project architect that we had to
take extreme care when working around the trees so we hired
a licensed arborist to come up with a plan to protect them,"
Broussard said.
Dufore's Tree Service of Ville Platte subsequently fenced
off the 10 trees and put mulch inside the fence perimeter
so that construction equipment would not injure the trees'
root systems.
A company representative also makes weekly site inspections.
"If a tree has to be trimmed, they have to do it,"
Broussard added. "Any time a tree is touched it has to
be by Dufore's." Only one tree was removed because it
lay in the middle of the school's building pad.
Ultimately, The Lemoine Co. will construct a single 82,000-sq.-ft.,
three-floor building that includes 15 classrooms, five laboratories,
auditorium, library, administrative offices, bookstore and
recreation room. The campus will centralize some the college's
classrooms that are currently scattered across Lafayette,
New Iberia and Franklin.
The project will be completed by November.
Broussard said the project is design/build, although all
of the design has been subcontracted to Architects Southwest
of Lafayette. Design of the campus began in October 2002.
"When we broke ground in August, the project was still
in design development," he added. "They released
the mechanical, sitework, electrical and plumbing package
so we could get started." Total design was finished in
November.
Starting construction before having completed designs created
some challenges, because "there are things you need to
coordinate while the structure is going up and you may not
know where certain components are going to be," Broussard
said.
Fill was hauled to the site to raise the building pad and
Gulf South Piling of Jefferson began driving more than 400
45-ft.-long wood piles as foundation. The forming and pouring
of concrete grade beams and pedestals followed.
Champion Steel of Alexandria furnished and erected the structural
steel for the building's frame.
"They topped out in mid February," Broussard said.
"The steel erection went perfectly and there were few
if any problems. A steel shortage hit the nation shortly after
the last piece of steel was erected.
A series of cold-formed steel roof trusses were fabricated,
pre-assembled and delivered to the site by Steel Source of
Irving, Texas, and Matrix Building Systems of Lafayette.
The trusses support a unique hip roof system with varying
transitions to resemble "a Creole residential style,"
Broussard said.
Joe Toher, a representative of Matrix Building Systems, said
the piecing together of the trusses "was a phenomenal
undertaking."
"There were numerous parts and pieces to assemble,"
he added. "The trusses were assembled in a factory in
Tyler and shipped to the site fully assembled. Not having
to stick-build the trusses in mid air is safer and faster."
A 7,400-sq.-ft. auditorium will have a cupola roof system
with an eight-sided configuration. The auditorium space will
be a simple open area with no permanent stage or seating so
that movable partitions can be used to create meeting spaces
of varying sizes.
The building's composite concrete slabs measure 4 to 5.5
in. thick and are reinforced with welded wire fabric. The
3,500 cu. yds. of 3,500 psi mix is being supplied by Baldwin
Ready-Mix and pumped into place.
"Right now, we're trying to get the building dried in
so we can begin interior wall framing and buildout,"
said jobsite superintendent Bobby Kadder. As a cost saving
measure, two unused chillers are being transported from Baton
Rouge Community College to provide cooling for the Lafayette
campus.
"A new central plant is coming on line in Baton Rouge
and to save money we're going to take their chillers and put
them here," Kadder said. "We expect to get those
at the end of June."
The exterior of the building will consist of a brick veneer,
cast stone and stucco, as well as glass and glazing. Synthetic
roof shingles will cap the building.
"There's a plaza area off the front of the structure
that will be nicely landscaped so that the students can sit
and mingle outside," Broussard said. A 260-car parking
lot will be paved off to one side of the building and across
a nearby street.
Interior work is highlighted by the building's aesthetic
main entrance, including a two-story vertical atrium, maple
wood paneling and terrazzo floors.
"The atrium is about a 24-ft.-tall space and the second
floor overlooks the lobby," Broussard said. "There
are also some glassed-in second floor offices that overlook
the atrium."
South Louisiana Community College's new academic complex
was made necessary by a more than 40 percent increase in enrollment.
Five more buildings are planned for the future.
The new building was financed by issuing tax-exempt bonds
through the Lafayette Public Facilities Trust Authority and
funding from the Louisiana Legislature. Once the bonds to
finance the new building are paid off the building will be
owned by the state.
The first campus of SLCC opened in 1998 with 36 students
in New Iberia. The system now has an enrollment of 1,533 with
other locations in Franklin and Lafayette. <<
Useful Source:
For more information about South Louisiana Community College,
go to: www.slcc.cc.la.us/
|