|
An historic proposition
Mid-1800 warehouses preserved
at New Orleans Marriott site
By Sam Barnes
An appreciation of history has been essential during construction
of a concrete parking basement at the new Marriott Convention
Center Hotel in New Orleans.
An owner stipulation that two 150-year-old warehouses be
incorporated into the $35 million hotel required some inventive
preliminary work so excavators and pile drivers could work
within the confines of the warehouse walls.
Three similarly sized cotton warehouses originally occupied
the site, but only two of the warehouses have historic significance.
The third was demolished to make way for the hotel's 14-story
tower.
"We had to brace the walls all the way around before
doing anything on the inside of the buildings," said
Ken Flower, project manager with design-build contractor Carl
E. Woodward LLC of New Orleans. Structural engineer Jeffrey
Thomas Avegno Inc. of New Orleans designed the bracing system.
Boh Bros. Construction LLC of New Orleans drove perimeter
sheet piles 6 ft. inside the basement walls to prepare for
the excavation. The 35-ft.-long sheet piles were left in place
to serve as forms for the basement floors and walls.
"After pouring the concrete for the basement floors,
it was physically impossible to pull the sheet piles out,"
Flower added.
All of the excavation had to be performed without the benefit
of a de-watering system, which would have negatively impacted
adjoining properties. To compensate, the Carl Woodward crew
performed numerous "mini" excavations.
"We'd excavate a small portion of it and immediately
put in a concrete dry bottom, while pumping out any type of
surface water," senior project manager Legier Kuhner
said. "We'd pour it against the sheet piles and lock
those in."
The basement slab reaches 5 ft. thick in pile cap locations
and the walls are 1 ft. thick. Once complete, the one-level
basement garage will reach about 50,000 sq. ft. and include
108 parking spaces.
Boh Bros. Construction drove timber and precast concrete
piles as foundation for the basement and hotel using a "follower"
to drive the piles to the desired depth.
"Because of our proximity to the Mississippi River we
knew the pile driving was going to be challenge," Kuhner
added. "In many locations the piles would hit 'refusal'
before getting to their final location. We'd just excavate
around it and cut the pile off."
"When it's all said and done, the warehouse walls will
look much like they did from the outside," Kuhner said.
Flower said there is currently a major push to get the hotel
dried in to the seventh floor by July so that mechanical and
electrical crews can begin work on the lower floors.
CECO Concrete Construction LLC of Slidell began construction
of the hotel tower with a significant shoring operation this
spring. The shoring is being performed in two phases, one
to build the hotel tower and one to build an adjoining two-story
section. Separate crews are performing each phase.
Nearly all of the concrete pours begin at 2 a.m. and finish
by 7:30 a.m.
"The hotel is made entirely of concrete, 95 percent
of which is post-tensioned with some minor reinforcing steel
in the two-story section," Flower said. The hotel's fourth
through 14th floors have 7.5-in.-thick slabs and the bottom
floors measure 8 in.
The lower floors will support a ballroom, lobby and restaurant.
The exterior of the building will be made of brick and glass
fiber-reinforced concrete panels supplied by GFRC Cladding
Systems of Garland, Texas. Precast erection was expected to
begin in late spring.
About 90 percent of the panels have already been manufactured,
Flower said. The architectural precast is being produced in
a variety of dimensions.
The deliveries will be made to the site "just in time"
and the panels will be lifted and placed directly from the
truck.
"We'll keep moving forward with the precast erection;
it should never really stop," Flower added. "We
hope to have the entire structure dried in by mid-October."
Mechanical work will require the installation of three large
chillers on top of the hotel tower and interior work will
include some aesthetic installations within the hotel lobby.
The hotel will have three elevators that service all floors
and one elevator that will service the first two floors.
"The lobby is going to have the nicest finishes, including
a lot of millwork cladding on walls and columns," Flower
said.
A ballroom on the first floor will have a two-story-high
ceiling and a steel joist and metal roof. Concrete beams measuring
up to 18 by 30 in. will run throughout the ballroom.
Carl Woodward performed design of the hotel as part of a
joint venture with Trapolin Architects of New Orleans.
"Trapolin has a lot of experience with building projects
in the downtown area and we felt their experience would greatly
expedite the project," Flower said. Although design began
in 2001, permit delays pushed groundbreaking to early 2003.
Once finished in May, the 331-room hotel will measure about
326,000 sq. ft. and have a 47,000-sq.-ft. basement.
Useful Resource
For up-to-date information about the hotel's progress, go
to: http://marriott.com/news/
|