|
A hybrid solution
Concrete garage to accommodate
Bossier's developing Riverwalk
By Sam Barnes
As rising fuel costs pushed the envelope this winter and
spring, 20 trucks lumbered down the interstate each day to
deliver structural and architectural precast concrete for
a new parking garage in Bossier City.
The $20 million hybrid garage is made of 6,500 pieces of
precast and 10,000 cu. yds. of poured-in-place concrete and
will accommodate the Louisiana Riverwalk retail development
along the Red River. Walton Construction Co. LLC of Shreveport
is building the garage.
Rising fuel costs prompted precast supplier TDI Parking of
Tulsa, Okla., to begin looking for a production area a little
closer to the site.
"We began doing some of the work in Dallas because
it's a lot closer to the jobsite than Tulsa (the main production
site)," said Gene Matthews, TDI erection manager. "Moving
some of the work there helped keep costs down." The structural
precast members were manufactured in Tulsa and Dallas and
the architectural panels that clad the garage exterior were
made in Little Rock.
Having to coordinate deliveries from three locations created
scheduling dilemmas for Matthews because no more than a day's
worth of precast could be stockpiled at Walton Construction's
laydown yard less than a mile away. This meant the precast
had to arrive "just in time."
"To make it work, we had a majority of the precast manufactured
before the job even began," he added. "We could
only produce about six precast components a day but we erected
about 20 a day, so we had to have more than half of them made
before the project started."
The four-level hybrid garage has a poured-in-place concrete
deck, which also lowers cost by reducing the foundation necessary
to support the garage.
Decking for the four-level parking garage required 4,500-psi
concrete supplied by TXI's Bossier City plant. The 5-in.-thick
elevated slabs are reinforced with post-tensioning cables.
Walton is pouring the first garage deck and TDI is pouring
the upper level concrete.
"To adhere to a tight schedule we're making two 9,000-sq.-ft.
pours a day,"said DeWayne Akins, general superintendent.
"We start at about midnight and pump them back to back.
By noon we're finished."
Placing the concrete during the early morning hours reduces
traffic complications and service problems from the concrete
supplier.
"We also get it down before the sun heats things up
and slows our setting time," Akins added.
Matthews said TDI is using a new flying form system at the
site to place the ready-mix for the upper garage levels.
"We've got a patented form that allows us to set up
to 10,000 sq. ft. of forms, get a rod buster on it and get
it poured the next day," he added.
The hybrid garage can be built faster than an all-precast
garage, Matthews said, "since precast has to have a three-
to four-month lead time to allow for production. Less precast
means less lead time." The garage design was initially
created by Culp & Tanner Inc. of Chico, Calif., to withstand
earthquakes "and we found that it works good everywhere,"
Matthews added.
Brad Roberts, project manager with Walton Construction, said
contractors were given the choice of bidding the project as
precast, cast-in-place or hybrid.
"To bid the job as hybrid we had to do a good bit of
re-design to existing plans by Carter & Burgess Inc. of
Dallas," Roberts said. "The re-design was figured
into the price of the hybrid system when we bid the job. Easier
constructability was the main reason we went with the hybrid
system. The project had a tight schedule and the hybrid system
seemed to be faster and easier to erect."
The decision appears to have been a wise one. The project
is running a few days ahead of schedule despite about 40 days
of rain delays since the project's December groundbreaking.
The garage will be finished in September.
L. G. Barcus & Sons of Oklahoma City had to drill about
1,200 14-in.-diameter, 65-ft.-deep shafts as foundation for
the garage. The process was originally expected to take 30
days.
"Weather really hit us hard during the middle of drilling
auger-cast piles and 30 days turned into more than two months,"
Roberts said.
To make up lost time, crews worked seven days a week when
possible.
Akins said the jobsite was formerly a residential area, so
site preparation required the removal of underground utilities
and some house slabs.
"We also installed a 42-in.-diameter concrete stormdrain
directly beneath the footprint of the new garage to facilitate
site drainage," he added.
Once out of the ground, the job progressed more smoothly.
"With much of the precast columns, beams and girders
already produced, it became a matter of just piecing the garage
together," Akins said.
By the end of April, all of the structural precast and one-third
of the architectural precast had been erected. Architectural
precast is "is colored a light brown and has some reveals,
but nothing really fancy," Akins said.
Other components of the parking garage include a lobby with
skylights, two elevators, two escalators and a stairwell.
"Eventually, the developer will work out a way to connect
the garage to adjoining buildings (that are not yet built),
but as of right now that's not in the plans," Roberts
said.
The crew is also building a road off of Bass Pro Shop Drive
leading to the new garage and installing a steel arched-culvert
bridge across a pond that was dug for landscaping purposes.
"We're still trying to push the project further ahead
of schedule," Roberts said. "There's a $10,000-a-day
bonus for finishing early, with no cap."
Useful Sources:
For more information about the Louisiana Riverwalk, go to:
http://www.louisianariverwalk.com/
|