|
Almost done
Next-to-last stretch of LA 15 four-laning
builds through wetlands
By Sam Barnes
Now that the nearly 7-mi. stretch of LA 15 that begins in
Sicily Island and stretches south to Greenville has been raised
above the surrounding wetlands, its progress should be unhindered.
Permitting delays created some problems at the project's
outset, since work in the wetlands area had to be approved
by the U. S. Army Corps of Engineers.
"Nothing could happen until the wetlands permits went
through, and that postponed work out there for a few months,"
said Ken Free, project engineer with the Louisiana Department
of Transportation and Development's Chase office.
Free said the $18.8 million project will create a four-laned
concrete thoroughfare through Sicily Island and asphalt lanes
for 5.4 mi. through a rural area.
Once finished, only one section of LA 15 will remain to be
four-laned to complete the entire corridor, which is funded
by the state's Transportation Infrastructure Model for Economic
Development.
"We're about 75 percent complete with the embankment
in the rural areas and are in the process of pouring concrete
in Sicily Island," Free added. "About 60 percent
of the subsurface drainage is also complete."
Diamond B Construction Co. LLC of Alexandria is the general
contractor and Denton-James Construction LLC of Baton Rouge
is performing excavation, embankment construction, subsurface
drainage and concrete paving.
Free said a significant amount of excavation is required
through Sicily Island, since the new southbound lanes are
being built in the path of abandoned train tracks.
"Although the tracks had been removed when the tracks
were taken out of service in the 1970s, there was a lot of
existing dirt embankment to remove," he added.
Once the embankment was brought "to grade," the
crew placed 6 in. of soil cement as a working table followed
by 8 in. of limestone and nearly 10 in. of concrete driving
surface.
"It's a typical Class A concrete mix supplied by Heck
Industries from an on-site portable plant," said Diamond
B project manager Ben Elkins. The concrete is not reinforced.
The northbound lanes through Sicily Island will follow the
route of the existing two-lane highway.
"There will be about 200 ft. separating the south and
northbound lanes when finished," Elkins said. Drainage
through the city sections will consist of curbs, gutters and
subsurface drain lines.
Construction of the 5.4-mi. rural section began with a massive
dirt moving operation to create the new southbound embankment.
"The majority of the fill is coming from off site,"
Elkins said, "but we also used some of the site excavation.
There's a total of about 440,000 cu yds. of embankment and
about 258,000 cu. yds. of excavation."
Paving of the rural section will begin this fall with construction
of a 6 in. soil cement "working table," followed
by 6 in. of asphalt base, 4 in. of asphalt binder and 1.5
in. of wearing course.
"The project was designed prior to the statewide implementation
of the Superpave mix design," Free said, "so we're
using a Type 8 wearing course produced by Diamond B out of
its Vidalia plant 20 miles away." The Superpave system
provides greater resistance to permanent deformation, fatigue
cracking and low temperature cracking with Hot Mix Asphalt
(HMA), and is currently designed into the specifications for
all new asphalt roads in Louisiana.
Once the southbound lanes are completed this winter, traffic
will be switched over and work will begin on the existing
road, which will be used as the northbound lanes when finished.
"We're removing about 60 percent of the road where
we need to adjust the grade or where there are foundation
problems," Free said. In those areas, 6 to 8 in. of asphalt
will be milled and its concrete base demolished and hauled
off-site.
The concrete was the original driving surface and had been
overlaid several times.
"The contractor will likely haul the concrete away
for crushing, and use it as road base on other jobs,"
Free said.
In locations where the soil is unstable, the contractor
will place lime to stabilize the area.
"Shoulders will measure 10 ft. outside the driving
lanes and 4 ft. inside, and will be made of 8.5 in. of stone
and soil cement topped with 1.5 in. of asphalt," he added.
A 57-ft. median separates the north and southbound lanes.
Drainage work requires the installation of reinforced concrete
pipe cross drains and open ditches.
Free said that as the four-laning of the LA 15 corridor
has progressed from Rayville to Vidalia, traffic flow has
increased through Sicily Island. More than $70 million has
been allocated for the corridor's four-laning.
"We have been four-laning LA 15 since the early 1980s,"
Free added, "and the only remaining section runs from
just south of Greenville through Clayton."
The Greenville to Clayton project, which includes a new bridge
over the Tensas River, is scheduled to begin in 2005 and finish
in 2007.
Useful Resources:
For updates on the progress of the LA 15 project, go to:
http://www.dotd.state.la.us/construction/chase.html#FRANKLIN
|