|
New Donaldsonville school built in
sugarcane field
Intricate truss system supports roof of multi-winged middle
school
By Sam Barnes
A new kind of crop is growing near Donaldsonville.
The new $11.3 million, 120,000-sq.-ft. Lowrey Middle School
is rising skyward as the sugarcane once did in a field on
the outskirts of town. The school will replace the town's
aging middle school when it opens this summer and will include
classrooms, auditorium, cafeteria, offices and gymnasium.
One of the more interesting aspects of the project is its
liberal use of structural steel.
"All of the building structures are made of steel,
and each of the building's wings gets some type of steel truss
with flat roofs around the perimeter," said Bruce Bacon,
superintendent with Woodrow Wilson Construction Co. Inc. of
Baton Rouge.
Outlaw Steel Erectors of Clinton is performing fabrication
and erection at the site, and had to erect the largest trusses
for the school's gymnasium.
"Six large trusses measuring about 100 ft. long arrived
at the site in halves," Bacon said. The two sections
were welded together on the ground and lifted and placed by
hydraulic crane on top of the school's gymnasium columns.
"They used a cherry picker during the assembly, but
a much larger 200-ton crane was used to place the big truss
sections."
The remaining trusses are significantly smaller, measuring
about 77 ft. in length.
Gary Hebert Architect of Plaquemine designed the school.
When the contractor broke ground in April, 6 in. of topsoil
was stripped from the site and followed by the placement of
25,000 cu. yds. of select fill to create the building pad.
Lime was added to the pad to "tighten up" the
soil and to achieve the specified 95 percent compaction. The
process took about five weeks.
"We also had to fill some drainage ditches that cut
through the middle of the property, then dig a retaining pond
to provide a new place for drainage," Bacon said. When
the school is finished, the pond will be filled and concrete
pipe will carry the stormwater to a canal near the property.
Fontaine Builders Inc. of Lafayette performed site work
and soil stabilization.
"We then formed up the building and put in spread footers,
grade beams and anchor bolts to support the steel columns,"
Bacon added. A 4-in.-thick floor slab was poured for the building,
supplied by Koch Material Co. of St. James, and pumped into
place.
A standing-seam metal roof caps the building and the exterior
will be made of brick, stucco and glass. Mechanical work requires
the construction of a mechanical room for chillers on one
side of the building.
"Inside the building and gymnasium we're installing
drywall and there's nice tile flooring throughout," Bacon
said. All of the steel columns are encased in metal studs
and sheetrock throughout the building.
Other work requires construction of a new drive from the
nearby highway and construction of an exterior steel and metal
bus canopy at the main entrance.
"There are also football and soccer fields as part
of the contract, where we'll have do some grading and put
in some select fill to get it to the height they want,"
Bacon said. Fontaine will begin the work this spring.
Chad Lynch, Ascension Parish School Board construction manager,
said the school system attends monthly meetings to "stay
involved in the project." He said the expanded capacity
of the school will enable the parish to accommodate population
growth in the area.
Lynch added that the school's most striking feature will
be its finished exterior colors, consisting of a blue-tinted
roof, colored trim and a buckskin-colored stucco.
"It's going to be very attractive - something that you'll
notice right away," he added.
Bacon said the project's fast-track pace is also noteworthy.
"Any time you try to build a school in a little over
a year, it's a challenge," he added. "No matter
what weather delays you encounter, you still have to finish
on time. There are no excuses."
Accomplishing the deadline means "keeping on top of
our crew and the subcontractors," Bacon said. "Nobody
wants to be hit with liquidated damages at the end of a job.
It's their responsibility to keep the job manned."
The site is close enough to Baton Rouge for it to affect
manpower availability.
"There are a lot of people around here interested in
working, but it still takes a while to get a good crew built
up," Bacon added. The crew at the site currently averages
about 60, including subcontractors.
"I'm here to make sure they get anything they need
to get the job done."
Useful Resource:
For more information about the Ascension Parish school system's
building plans, click
here>>
|