|
Cloning history
Hale Hall torn down, replicated
at Louisiana Tech
By Sam Barnes
Students and faculty will be looking at a clone when they pass
by Louisiana Tech University's Hale Hall this spring.
Asbestos abatement and required code improvements edged the
proposed renovation of the 105-year-old Ruston building over
budget, so both the designer and university began weighing
other alternatives.
Ruston architect Mike Walpole said erecting a new building
with a different, more modern design was never discussed.
"I think the vision of the university president, Dan
Reneau, and the donor was to preserve the original appearance
of the building whether through renovation or a total reconstruction,"
Walpole added. The anonymous donor gave $1 million for the
effort.
Ultimately, everyone agreed to replicate Hale Hall in its
original location, but cost savings still had to be found
to bring the project within budget.
"There were some structural things that we ended up
simplifying and some areas where we used more standardized
details," Walpole said. "For instance, the original
building had a rotated axis stairwell and we ended up eliminating
the rotated axis and just made it parallel to the existing
cavity."
The $6.1 million reconstruction of the building by Triad
Builders of Ruston was ultimately bid nearly $3 million cheaper
than the original renovation plan. The job will be completed
in March.
While the exterior of the building will be identical in
appearance, except for certain fire code and handicapped accessibility
improvements, the interior of the building will look nothing
like the original.
"Hale Hall was constructed as a women's residence hall,"
Walpole said. "It was expanded and became a men's residence
hall, then a classroom and art studio facility. In fact, my
first architectural studio was located there in the 1970s."
The new Hale Hall will be used by the university's School
of Architecture and will have classrooms, studios and offices.
The exterior appearance of the building - a "French,
Second Empire" design - has mansard roofs, turrets and
classical details such as quoins, tall arched windows and
molded "surrounds."
Although identical in appearance, modern materials are being
used in lieu of existing materials in some locations, including
molded plastic instead of wood around window frames, aluminum
framing instead of wood and rubber shingles instead of asbestos
shingles.
Little was done to try to match the brick color of the original
building.
"The bricks weren't consistent because at some point
they had been painted, so we weren't too concerned about blending
the brick," Walpole said. "The new brick color matches
many existing buildings at the university."
Ideal Masonry of Crossett, Ark, installed about 100,000 bricks
for the building.
When work began at the site in November 2002, Triad Builders
and subcontractor Lou Chandler of Bossier City demolished
the existing building and foundation.
Elliott Atkins, Triad Builders' general superintendent,
said asbestos abatement had been completed as part of an earlier
contractor.
"Using backhoes, the Chandler crew basically grabbed
the walls and tore them down," Atkins said. "They
picked a starting point on the third floor and tore down the
outside wall, and that one section of roof. The roof fell
onto the third floor, and they came on down with it floor
by floor."
Underground foundations, consisting primarily of brick footings,
were also removed.
"Fortunately, we didn't run into anything unexpected
and the demolition went smoothly," Atkins said. "We
removed the footings, brick, wood and glass. Other than the
steps and sidewalks, there was almost no concrete associated
with the building."
Triad Builders waited until demolition was completed before
moving on site. The first order of business was to haul fill
dirt to create a building pad.
"Although the finished floor elevation of the building
was close to the original, the ground floor had been made
of wood so we had to fill that area with dirt before pouring
concrete," Atkins said.
A 40- by 100-ft. basement on the south end of the building
required additional fill.
"New spread footings were 7 ft. deep in the basement
area and the rest of the footings were 3 ft.," he said.
Footing construction was followed by a 5-in.-thick reinforced
slab made with 3,000 psi concrete supplied by Century Ready
Mix of Monroe. Hercules Inc. of Monroe pumped most of the
concrete for the project.
The structure of the new building is made of steel erected
by F&R Steel Erectors of Mississippi. Limited laydown
areas made steel erection difficult.
"We had to stage that to get it done," Atkins
said. "They couldn't deliver the steel too early or too
late. It had to be just in time."
As soon as the steel was far enough along, the contractor
began pumping second- and third-floor concrete along the north
end of the building. The elevated slabs are 3 in. thick and
are reinforced with wire mesh.
Lightweight concrete was then pumped for the building roof.
"Mechanical and electrical subcontractors had to install
their rough-ins before pouring the floors," Atkins said.
"To stay in succession, once the lightweight concrete
was poured, we had our drywall contractor start framing metal
studs and exterior walls on all the floors."
A single elevator shaft was framed and poured, and three
sets of stairs were installed to provide access to the upper
floors. Mechanical work required construction of a separate
building with a new chiller but an existing steam line will
provide heat.
Atkins said several other architectural features are being
installed on the exterior to match the existing building.
"We're installing a special high-density foam material
in place of wood for the window trim and corner trim,"
he added.
In addition, 1,500 ft. of copper gutter borders the perimeter
roofline, but serves no practical purpose.
"The gutter has a top on it, so water can't drain from
it," Atkins said. "Essentially, they wanted the
new look to match the old building. The only way to do that
was to put a gutter up there."
The water will instead drain through roof drains scattered
across the top of the building.
Also, exterior shingles made out of rubberized neoprene
are being used instead of asbestos and aluminum instead of
wood for window frames.
Inside the new Hale Hall, two large studios measuring about
6,000 sq. ft. each will be located on the second and third
floors.
"They're basically big open spaces," Atkins said.
"Tech will install their equipment in there once we're
done." The ceilings in the studios leave the building
structure exposed, while the remaining classrooms and offices
have suspended ceilings.
An admissions area on the first floor will have the most
decorative features in the building, including hardwood floors,
carpeting and millwork.
|