|
Market Outlook: Highways
TIMED breaths life into declining highway construction
revenues
By Sam Barnes
Highway contractors are thanking the heavens for Louisiana's
Transportation Infrastructure Model for Economic Development.
Declines in federal transportation dollars have been replaced
with a surge in money from the TIMED program, and just in
the nick of time.
The Louisiana Department of Transportation and Development
let to contract 318 construction projects totaling approximately
$534 million last year, representing a $12 million increase
over the previous year's lettings..
"Our targeted spending on the TIMED program this year
was $162 million," DOTD Secretary Kam Movassaghi said.
"We actually let 20 TIMED construction projects valued
at $172 million. Additionally, we completed seven TIMED project
segments, two clearing and grubbing contracts and 29 miles
of new highway."
"The accelerated schedule of the TIMED Program has
DOTD opening bids for construction every month over the next
few years to ensure all construction is underway by 2008,"
said Buddy Porta, DOTD TIMED Program spokesperson.
The TIMED program is the single largest transportation program
in Louisiana history. The $3.5 billion improvement program
includes widening 500 miles of state highways to four lanes
on 11 project corridors, widening and/or new construction
on three major bridges and improvements to both the Port of
New Orleans and Louis Armstrong International Airport.
The program is designed to enhance economic development
in Louisiana through an investment in transportation projects.
Some recently bid TIMED projects include:
- The $14.7 million four-laning of U.S. 167 in Bernice.
Construction of the segment is also scheduled to begin in
the next several months.
- The $12.6 million four-laning of US 167 project in
Dubach. Construction is scheduled to begin in the next several
months. The 2.6-mile segment will be widened to five lanes
through the town.
- A $12.2 million segment of West Napoleon Avenue in
Jefferson Parish.
- A $6.28 million embankment project between North
Hodge and Quitman on U.S. 167.
Federal budget figures for the current fiscal year are less
optimistic. Last year, DOTD received approximately $460 million
in federal money, with about $50 million dedicated to certain
projects, in addition to a state match of 20 percent for most
of that amount.
To measure DOTD's success in the minds of its public, the
department recently conducted a statewide customer satisfaction
poll.
Overall, the 1,600 respondents gave a grade of C+ to the
job being done by DOTD on the state's highway system.
"We did this because we wanted to know what our customers
saw as our strengths and weaknesses and which areas we needed
to improve," Movassaghi said. "While our overall
grade of C+ is not where we want to be, it is certainly a
good starting point."
In addition to receiving an overall "fair" grade,
DOTD was graded on various components of the state's transportation
system, such as traffic flow (C+), pavement conditions (C),
bridge conditions (B-), road maintenance (C+), work zones
(C) and safety of roads (C+). Respondents were also asked
whether the state highway system was better, worse or the
same as it was five years ago. Forty-five percent of the respondents
said better, 41 percent said the same, 12 percent said worse
and 2 percent didn't know.
As part of its 2002-2006 Strategic Plan, DOTD seeks to achieve
a 60 percent customer satisfaction rate.
Projects
I-10, New Orleans. James
Construction Group of Baton Rouge currently has two contracts
to widen two sections of both the east and westbound lanes
of Interstate 10 in New Orleans. A $60 million contract stretches
from the Southern Railroad Underpass to the Carrollton Avenue
Overpass, while another $30 million contract goes from Clearview
Boulevard to Causeway Boulevard.
Switching to nighttime work hours for the Clearview to Causeway
section has been easier said than done. Since work and material
deliveries proceed more slowly at night and some job costs
have increased, the deadline for the project was pushed back
from October to December.
The Southern Railroad to Carrollton project began in October
2001 and will widen 5,360 ft. of driving lanes both east-
and westbound by 28 ft., all the while not closing a single
lane of traffic.
All of the widening for the section takes place on the outside
lanes.
"For the on-grade portions, we're building up the embankment
and placing 2 ft. of sand, 9 in. of limestone and 9 in. of
asphalt driving surface," project manager Rodney James
said. Existing shoulders had to be demolished to make way
for the new road sections, requiring more than 20,000 sq.
yds. of asphalt and road base removal.
About 2,700 ft. of elevated interstate bridges entail more
difficult construction, including new pile-supported columns
and caps. About 4,000 cu. yds. of structural concrete is being
placed for the bridge sections.
"On I-10 westbound, we're building one additional column
with a cap, but half of the eastbound bridges are being done
with one column and cap and the other half is getting two
columns and caps to accommodate a ramp," James said.
All six existing ramps are being realigned to accommodate
the widened interstate.
Once the new widened sections are complete, the contractor
will mill the existing driving surface and come back with
new asphalt across all six lanes. About 32,000 tons of asphalt
will be placed for the entire project.
A new pump station comprising about one-third of the job,
a new pump station will alleviate a drainage problem at the
railroad underpass. To build the pump station, the James Construction
crew drove sheet piles to create a cofferdam surrounding the
150-ft. by 90-ft. site, then drove approximately 340 steel
pipe piles with an ICE diesel hammer, and excavated enough
soil to brace the cofferdam. The 14-in.-dia. piles measured
50 ft. long.
A double barrel, 10-ft. by 8-ft. box culvert will run between
the service road and I-10, as well as beneath the interstate
in one location. The culvert will transport drainage water
1,200 ft. from the underpass to the pump station. Similar
to the pump station's construction, a cofferdam was built
around the box culvert site, measuring about 48 ft. long and
about 25 ft. deep.
Upon completion, the box culvert (with 1 ft. walls) will
be backfilled with onsite excavated fill.
"We're installing some steel discharge pipe on the
discharge side, furnished by Northwest Pipe, that will transport
the water out of the pump station," he said. Three of
the four pipes measure 72 in. diameter, with the fourth reaching
48 in. dia.
About 300, 14-in.-sq., 60-ft.-long precast concrete piles
were driven by Gulf South Piling & Construction Inc. of
Jefferson to support the discharge pipe.
Other work on the Southern Railroad underpass to Carrollton
section requires the installation of about 2,400 lin. ft.
of 84-in.-diameter reinforced concrete pipe running parallel
to the eastbound lanes of the interstate. The pipe will connect
to the box culvert that leads to the pump station.
James said the road paving portion of the project will be
completed by March, with the pump station to be completed
the following summer.
The second contract, stretching 9,300 lin. ft. from Clearview
to Causeway boulevards, is being performed almost entirely
at night.
Construction, which began in September 2002, should also
be finished in December.
US 190 from LA 983 to LA 1, West
Baton Rouge Parish. A project under construction in
West Baton Rouge Parish will continue widening the median
of US Highway 190 for another 7 mi. through West Baton Rouge
and Pointe Coupee parishes.
The project will connect to a completed project to the east.
Mika McKee, project manager with general contractor F. G.
Sullivan Contractors, Baton Rouge, said that after a lengthy
utility relocation phase crews began construction of the new
westbound lanes.
"We're placing 12 in. of lime, 10 in. of base, then
10 in. of asphalt," McKee said. Each of the east- and
westbound roadways will measure approximately 40 ft. wide.
The widened median will reach an average of 50 ft. wide
everywhere except a section of the roadway that extends through
the town of Erwinville, where a five-lane roadway will be
constructed.
McKee said the new westbound lanes should be completed by
this fall, when traffic will be rerouted to the new lanes.
The project is one of the first projects in the state to
be let as an "A+B+C" contract, which considers the
life-cycle costs and speed of construction during the bid
process, and allows asphalt and concrete to compete for the
same project.
On US 190 to the west, a piece of history is being rebuilt
in St. Landry Parish as three pairs of aging two-lane bridges
are replaced to accommodate current traffic load.
The 50-year-old bridges cross a major floodway and two bayous
in St. Landry Parish east of Krotz Springs.
Kyle Flettrich, field project manager with Boh Bros. Construction
Co. Inc. of Baton Rouge, said the bridges that cross Slow
Bayou and Darbonne Floodway are in close proximity to one
another, while the third - Cortableau Bayou Bridge - is separated
from the others by a mile of roadway.
The project was delayed shortly after groundbreaking in
November 2002 while Boh Bros. waited for completion of an
adjoining section of roadway, but once construction resumed
in February, traffic management became the next major concern.
Traffic was to be put onto the two eastbound lanes, allowing
demolition of the bridges' westbound lanes to begin.
"Rather than close down traffic the entire length of
the jobsite we opened it up between Darbonne and the other
bridges," Flettrich said.
"This eased the traffic flow a bit, but it also saved
money because we didn't have to put concrete barriers up the
entire way."
Flexifloat barges are used when working from the water during
both the demolition and reconstruction phases.
During the demolition, the bridges are being taken down in
their entirety, including decking, piles and pile caps. The
piles are then cut off below ground.
Coastal Bridge Co. Inc. of Baton Rouge began driving piles
for the first of the new bridges in April. Several of the
piles reach 125 ft. long in locations where a layer of sand
strata was deeper and harder to reach.
Boykin Bros./Louisiana Concrete Products of Baton Rouge
is supplying all the piles, totaling more than 700. The remainder
of the piles range from 60 to 80 ft. in length, and average
24 in. sq. Piles were driven plumb and at a "batter"
to support the numerous bents for each bridge.
"Total completion is scheduled for late 2005,"
Flettrich said, "but we are ahead of schedule and I think
we'll finish earlier than that."
LA 28, Vernon Parish. A
7.2-mile stretch of LA 28 in Vernon Parish is being widened
to four lanes as part of a $22.3 million project.
Justin Reeves, project manager with general contractor Gilchrist
Construction Co., Alexandria, said the project requires the
construction of new westbound lanes and the total reconstruction
of the existing lanes (which will later serve as eastbound
lanes).
"We're also reconstructing three bridges and building
three new bridges in each lanes," Reeves added. All of
the bridges reach three spans, with one "in a curve and
on a skew, but they're all fairly small."
Most challenging at the project's outset was "flattening
out" the hilly terrain with more than 950,000 cu. yds.
of excavation and hauling about 480,000 cu. yds. of material
for embankment.
"We had to filled in low places and cut down some hills,
and even on some existing road we're going to flatten out
the vertical places," he said.
Gilchrist plans to open a 4- to 5-mile section of the new
lanes this summer, and work will begin on the existing lanes.
"Once we get the dirt to the right grade, we'll cut
12 in. of lime, then 12 in. of limestone for stone base and
lay hot mix. It'll be about a 5-in. layer of mix," he
said. Nearly 100,000 tons of asphalt will be placed throughout
the duration of the project.
The entire project should be completed this spring.
LA 15 from Greenville to Sicily
Island. Diamond B. Construction Co. Inc. of Alexandria
is widening a new section of roadway to four lanes from Sicily
Island to Greenville.
Project manager John Harrington said the $18.8 million project
requires the widening of the road to four lanes, clearing
and grubbing, removal of existing pavement, removal of surfacing
and stabilized base, grading, drainage structure construction,
base course and lime treatment.
Engineering was performed by DOTD.
|