|
Working in a rice paddy
Contractor slogs through site to build new Jennings school
By Sam Barnes
A contractor slogged through a rain-soaked 40-acre site
last spring to raise a new high school building pad out of
an abandoned rice field.
With a little ingenuity and a lot of soil replacement, Bessette
Development Corp. of Lake Charles successfully accomplished
the task. The pad now sits about 2.5 ft. above the surrounding
cropland.
"We essentially took off about 2.5 ft. and came back
with 5 ft. of new soil," said Bessette Vice President
Sam Cavys. A scarifier machine mixed stabilizing lime into
the soil to stabilize the pad.
Once complete in late 2004, the $24 million Jennings High
School complex will include about 255,000 sq. ft. of buildings,
a gymnasium and football, baseball and softball fields.
"You won't be able to fit another building on the site
when we're through," Cavys added. "We're using up
all of the space."
Bessette, with the assistance of Live Oak Earthworks LLC
of New Iberia, initially stripped the soil from the site.
"We de-grassed and excavated the site with bulldozers,
put the dirt into rows and dried it for hauling," said
jobsite superintendent Brent Ardoin.
More than 20,000 cu. yds. of material was excavated, with
about 15,000 cu. yds. stockpiled onsite for use as topsoil.
Port Aggregates of Jennings supplied an additional 25,000
cu. yds of new select fill.
All of the fill meets 14 percent soil moisture and 92 percent
compaction requirements, as specified by the project engineer.
Due to the site's unstable soil, about 780 drilled shafts
ranging from 18- to 48-in. diameter are being drilled by Foundation
Drill Shafts Inc. of Sulphur as additional support for the
buildings. The shafts range from 17 to 27 ft. deep.
"All the shafts that exceed 18 ft. deep are being cased
to prevent groundwater seepage," Ardoin added. The contractor
is drilling a hole 1.5-in. diameter larger than the shaft,
placing the steel casing, then drilling through the casing
to the desired depth.
"The casing helped keep the sides of the hole from collapsing
during the drilling operation," Ardoin said. "It
all went smoothly." The shallower shafts did not need
to be cased.
Louisiana Testing & Inspection of Lafayette performed
extensive boring of the soil during the preliminary site work,
"so we knew what to expect out here," he added.
After the drilling operation, reinforcing steel was placed
into each shaft and concrete was pumped into the hole. About
1,800 cu. yds. of 3,500 psi concrete were placed into the
shafts, all supplied by Angelle Concrete of Sulphur.
The shafts were clustered throughout the school complex
to support structural steel load points, typically three shafts
per pile cap.
"The larger, 48-in.-diameter shafts were needed in
the gymnasium area as support for its large steel columns
and trusses," Ardoin said. The gymnasium will reach about
31 ft. at its highest point and will have a roof supported
by 109-ft.-long girder trusses. The remainder of the gym will
be built with concrete block and brick masonry.
The pile caps and floor slabs for the school complex will
require approximately 9,000 cu. yds. of concrete, much of
which contains super plasticizer to provide more slump.
"You can take a 3-in. slump concrete, add the 'Super
P' and get 8 in.," Ardoin said. "It gives us more
time to work with the concrete when pumping the slab on grade."
The 4-in.-thick structural slabs will be reinforced with
mesh and placed on top of 4 in. of gravel and a 10-mil polyvinyl
vapor barrier to provide additional fortification against
soil instability.
The erection of about 500 tons of structural steel began
in September and will be followed by concrete block and brick
and then interior drywall partitions. The steel frame will
allow the buildings to meet heavy wind-load requirements,
and should be completed this month "if the weather holds."
Albert K. Newlin Inc. of Lake Charles is performing both
electrical and mechanical installations at the site.
"There's three science labs in the building, so there's
a lot of piping to support that," Ardoin said. "The
HVAC system consists of a simple residential system with nearly
100 units."
The interior of the building will consist predominantly
of drywall and concrete block.
Wayne Corne of designer Corne-LeMaire Group of Lafayette
said the finished school complex will include 39 classrooms
and some interesting design elements in the school's entranceway.
The roof of the building will consist of some metal and some
built-up. All of the buildings are tied together by covered
walkways.
Other work calls for the construction of 200,000 sq. ft.
of exterior asphalt parking.
"We expect to have about 200 working out here at peak
next spring, when most of the subcontractors will be in full
gear," Bessette's Cavys said.
Despite some weather delays in June and July - nearly 30
in. of rain fell - Cavys expects to finish the project on
schedule.
Resource info:
For more information about drilled foundation construction,
go to:
http://www.adsc-iafd.com/
For more information about the progress of the high school
project, go to: http://webserver.jeffersondavis.org/
|