|
Sinking down
Contractor digs deep to re-build New Orleans runway
By Sam Barnes
Nearly 45 in. of asphalt had been piled on top of New Orleans
International Airport's Runway 1-19 by the time Boh Bros.
Construction LLC began the runway's reconstruction last spring.
Over the years, the heavily used north-south runway had
been sinking, and placing more asphalt to bring it back to
grade had become a quick fix.
"On the northern end of the runway, where the planes
touch down, there were numerous layers of asphalt," said
Roy Mouledous, jobsite superintendent with the New Orleans-based
contractor. "And that was on top of a layer of sand and
a second runway built 30 years ago.
"In effect, there were two complete runways stacked
on top of each other, both sinking into the ground."
And with each new lift of asphalt, the sinking worsened.
The current $25 million project should solve the problem,
with the existing top runway completely replaced with a super-thick
slab of concrete reaching 16 in. on top of sand and limestone.
And leaving the oldest runway slab in place should further
slow future sinking.
When work began last spring, the 1.5-million-sq.-ft. project
was divvied up into three phases, stretching from south to
north for 7,000 ft.
Work on the middle, 1,200-ft.-long phase two section began
first because it intersected the airport's east-west runway.
"We were approaching June and the airport needed us
to get that section done fast," Mouledous said. "The
air is lighter in the summer and the planes need more runway
to achieve lift. Having a shorter east-west runway meant the
airlines had to lighten their loads to achieve the required
threshold, and they don't like to do that."
The crew had a 20-day window to perform the entire phase.
"We had to mill the old runway, break up the concrete,
excavate it, put the sand and stone in, pave it, then get
out," Mouledous added. "They were flying right over
us during that period of time."
Once phase two was completed, crews began milling the 600-ft.-long,
phase one section at the southern end of the runway near the
airport terminal. Midwest Asphalt Corp. of Gainesville, Texas,
performed the milling for all three phases, often working
16 hours a day.
The phase three section is the longest at 5,200 ft., and
was completed in early October.
"They (Midwest Asphalt) had five machines going continuously,
milling to depths ranging from 9 in. to 45 in.," Mouledous
said. "One very large area had depths of 30 in."
The machines typically made several passes during the process,
milling 2 to 3 in. per pass.
Antigo Construction Inc. of Antigo, Wis., then broke the
10-in.-thick concrete runway slab beneath the asphalt with
guillotine hammers, excavated and hauled the concrete for
crushing and recycling.
For the new runway pavement, the Boh Bros. crew placed 1
ft. of sand, a layer of geotextile fabric and 8 in. of limestone.
The limestone was graded using "stakeless grading,"
which relies upon Global Positioning Systems technology. The
grading method helped the contractor achieve more accurate
machine and blade positioning in real-time, thus reducing
both time and cost of construction.
"Once they compacted it and got it to grade, we came
in with the paving crew and started placing concrete,"
said paving superintendent Ken Bordelon.
An on-site batch plant operated by Lafarge Corp. of Metairie
supplied 750 psi flexural strength concrete for the paving
operation. About 100,000 cu. yds. of concrete were ultimately
placed for two lifts of concrete totaling 16 in. deep.
Bordelon said a large paving train helped maintain a continuous
paving operation.
"The concrete, after being delivered by truck to the
paving site, was dumped into a belt spreader that distributed
the concrete in an 11-in.-thick lift," he said. A strong
wire mesh was placed on top of the first lift, followed by
5 in. of additional concrete placed by a slip-form paver.
"We set a goal of about 1,800 cu. yds. of concrete
a day, and most of the time we achieved that," Bordelon
added. "We split the pours into equal increments determined
by the capacity of the batch plant and how many trucks we
could run." A crew of 13 people was needed during the
paving.
A little creativity was required when the contractor had
to build a new crossover connecting the north-south runway
with a parallel taxiway. Since the crossover had to be built
in an undeveloped area, the project engineer decided that
foam blocks would provide the best pavement foundation.
"That's virgin ground that had never been built on,
so the new pavement would have sunk at a faster rate than
the paved areas it connected to," said project engineer
W. O. Johnson of W. O. Johnson & Associates Inc. of New
Orleans. To compensate for that, the engineer specified 4
ft. of foam block, 4 in. of concrete, 16 in. of sand and 8
in. of limestone, all topped with 16 in. of concrete.
A holding bay area on the northernmost end of the runway
required similar foam block construction. Phylway Construction
Co. of Thibodaux performed all of the excavation and placement
of the foam blocks.
While they were waiting on the concrete to be poured on top
of the blocks, Phylway put concrete barricades along the perimeter
to keep the blocks from floating during a rainstorm.
Other work required the milling and asphalt overlay of two
jet engine "blast pads" at the northern and southern
ends of the site.
Roy Williams, director of aviation at the airport, said
two grants totaling $10.2 million were provided by the Federal
Aviation Administration to help fund the project.
"It has been over 20 years since this runway was last
rehabilitated," Williams added. "The New Orleans
Aviation Board made the decision that patching and filling
the runway was not enough. For the long-term benefit of the
airport, the airlines and the communities surrounding the
airport, we decided to go forward with a complete rehabilitation."
About $6.3 million of the grant for the runway rehabilitation
project came from discretionary funds.
"This is especially significant when much of the discretionary
funding this year is being devoted to security projects,"
Williams said. Another $2.4 million came from entitlement
funds that are derived from a formula based on the level of
passenger activity at a facility. Also included in the grant
is $1.5 million for a noise mitigation program. These funds
are to continue an ongoing sound insulation program.
To date, the airport has received a total of $20 million
in grants for the rehabilitation project.
Useful Resources
For more about future projects and initiative of the Federal
Aviation Administration, go to: http://www.faa.gov/AboutFAA/FlightPlan.cfm
|