|
War veterans get new locale near
Jennings
Void forms accommodate expansive clay soil
By Sam Barnes
McKee & Deville Consulting Engineers of Baton Rouge had
to find a way to protect three new concrete slabs from unstable
expansive clay soil during construction of a new $15.8 million
Southwest Louisiana War Veterans Home near Jennings. The veterans
home complex will provide medical care and nursing home care
to disabled and homeless Louisiana veterans upon its completion
in April 2004.
Danny Deville of McKee & Deville said after weighing alternatives,
cardboard void forms were determined to offer the best protection
for the slab.
"The void forms will rot over time, leaving a small void
beneath the concrete that creates the space the clay needs,"
Deville said. Without the void, the clay could push against
the slab and cause cracking. A double matting of reinforcing
steel provides extra support for the slab over the voids.
The use of the cardboard forms is a common method for compensating
for expansive clay soils, he added.
"Jennings is well known for its expansive clay problems,"
Deville said. "Nearby Crowley is the same way. The clay
out there has a high plasticity index."
Trent Descant, project manager with general contractor M.
D. Descant Inc. in Lafayette, said the bad soil was a problem
when his crew broke ground in May 2002.
"It was a very messy, wet jobsite, which left us in a
quandry from the very beginning," Descant said.
A network of nearly 1,000 drilled shafts, which provide additional
slab stability atop the clay, was difficult to pour at the
outset because roads into the 40-acre site had not been completed.
"It rained a lot while we were drilling, which made it
impossible for the trucks to get to the pour locations,"
Descant added.
His crew placed 3,500 yds of concrete for the shafts, all
from a hopper since they couldn't get the concrete trucks
to the building pad. "We had to pour everything with
a 2-yd. bucket," he added. "We hooked it up to an
exacavator, then walked it over to the holes and poured the
concrete." All of the fill for the building pads came
from on-site, derived from approximately 10,000 cu. yds. of
excavaton for a 4-acre pond at the front of the building.
After the pouring of the drilled shafts, the concrete void
forms were installed by the M. D. Descant crew.
"During the process, we'd grade the soil off, place the
4-in. void forms and put in 2 in. of sand to keep them level,"
Descant said. "We then placed the form, covered it with
plastic sheeting, put a rebar mat on top of that and poured
the concrete." All of the forms were supplied by Trak
Foundations of Beaumont, Texas.
The slabs were poured 6 in. thick with 3,500-psi concrete
supplied by Angelle Concrete's Jennings batch plant, located
"just a couple of miles away." A total of about
9,000 cu. yds. of concrete will be placed for the entirety
of the project.
Designed by Guidry-Beazley Architects of Lafayette, the Southwest
Louisiana War Veterans Home complex will consist of more than
92,000 sq. ft. of buildings.
The largest building by far is the main nursing home building,
while two smaller buildings, measuring 3,000 sq. ft. and 2,800
sq. ft., will support maintenance and arts & crafts. The
buildings are connected by covered walkways.
Leading to and surrounding the one-story buildings are approximately
200,000 sq. ft. of paved drives and parking areas.
Descant jobsite superintendent Neil Thevenot said after a
portion of the concrete slab had been finished in February,
his crew began erecting structural steel. The last of the
steel was erected in late June.
"As we've worked on the steel in some areas, other phases
of the work were going on," Thevenot said. "Drainage,
fire line, sewer, electrical and masonry are all going at
the same time."
Site drainage proved significant, with a lot of reinforced
concrete pipe installed to divert stormwater to the pond.
"About 2,500 lin. ft of RCP ranging from 18 to 36 in.
in diameter take the water to the pond site," Thevenot
added. "All site drainage goes there." A gazebo
will be built over the pond.
As of mid June, the crew at the site "had four patient
wings studded up, the administrative area studded up,"
and subcontractors were installing ductwork, laying masonry
and beginning roof construction.
The exterior veneer of the building will consist of 4 ft.
of colored split-faced concrete block, 3 ft. of glazed tile
and a top band of brick.
The roof consists of metal trusses over all the wings, topped
with metal decking, 2 in. of insulation and a standing seam
metal roof. The centerpiece of the mechanical phase of the
construction consists of chillers in a mechanical courtyard.
Larry Guidry, a principal with architect Guidry-Beazley Architects,
said the most notable design features of the main building
are the high-pitched ceiling areas within the entranceway
and the clerestory windows that line the administrative corridors.
"There's also some exposed decorative steel framing through
the corridors of the administrative area," Guidry added.
|