|
Concrete towers rise next to Natchitoches
hospital
Project adds new outpatient facility, creates office space
By Sam Barnes
Four concrete towers that provide the focal points of a new
outpatient facility are taking shape in Natchitoches.
Skip Converse Inc. of Alexandria began forming and pouring
the elevator and stairwell towers last spring on each side
of a new two-story facility that is being built adjacent to
the seven-story Natchitoches Parish Hospital.
The contractor broke ground at the site for the 65,000-sq.-ft.
facility late last year. The project also includes approximately
35,000 sq. ft. of renovations to the existing hospital.
The new outpatient facility will physically connect to the
hospital's first and second floors, although the tie-ins won't
take place until the project's renovation phase. Baton Rouge
architect Bradley-Blewster & Associates designed the new
addition, with assistance from Natchitoches architect George
Minturn.
Randy Deloache, project manager with Skip Converse, said the
tallest of the concrete towers will house twin elevator shafts
at the hospital's entrance, and measures 60 ft. tall. Another
tower will be 45 ft. tall and house a stairwell and elevator
shaft, and the remaining two 30-ft. towers will house emergency
exit stairwells.
"They're all being built with poured-in-place concrete
using a Symons form system," he said. "We're either
placing the concrete with a pump, or by crane and bucket."
Each tower wall measures about 8 in. thick and is reinforced
with a double matting of reinforcing steel.
Deloache said structural steel erection will begin once the
towers are completed this summer. Concrete slab construction
will soon follow.
"To be able to accept the structural steel, the towers
need to be in place," he added. "We expect the steel
erection to begin in August, and we'll top out about two months
after that."
Carl Riche, vice president of Skip Converse, said site demolition,
including the removal of existing parking areas, began last
fall, and was followed by the installation of 300, 40-ft.
deep, 18- to 24-in.-diameter auger cast piles by L. G. Barcus
& Sons Inc. of Kansas City, Kan. The shafts were completed
in March.
"There was an existing parking area that we completely
removed prior to constructing the shafts," Riche said.
Weather proved problematic during the project's early stages,
particularly the "extremely wet" months of January
and February.
"We still managed to get the shafts in rather quickly,"
Riche said. "The auger cast foundation system is a relatively
fast and easy method of foundation construction."
About four to five auger piles were constructed for each pile
cap. The slab pours, which began this summer, consist of a
5-in.-thick ground floor slab with reinforcing steel and a
4-in.-thick second floor slab poured on metal decking. The
second-floor slab is made of lightweight concrete and will
be poured in September.
About 2,500 cu. yds. of concrete, all supplied by Builders
Supply Co. Inc. of Shreveport, is necessary for the entire
addition.
Deloache said both the fabrication and erection of the 1,000
tons of structural steel necessary for the building structure
will be performed by Confab Engineering & Welding Inc.
of Shreveport.
Connecting to some of the steel members on top of the building
will be a new aluminum heliport installed by Heliport Systems
Inc. of Morristown, N.J. The heliport will have access to
the existing hospital through a nearby elevator tower.
"The structural steel actually comes up through the roof
system to accept the attachments of the heliport's aluminum
framing," Deloache said.
A "heavy mechanical" phase inside the building will
require the installation of new medical gas piping, as well
as conventional HVAC duct. Republic Contractors Inc., Shreveport,
is performing the work, which also includes the installation
of a new chiller within the existing hospital's mechanical
room.
River City Electric Co. of Monroe is performing the electrical
installation.
Other inside work includes the installation of metal stud
and gypboard walls, acoustical ceilings and various types
of resilient flooring and carpet.
"The exterior of the building will match the existing
hospital and will include an EIFS system, glass and glazing,"
said architect George Minturn.
"There's some brick veneer in certain areas, but for
the most part it's EIFS and glass, which matches the exterior
of the hospital as it is now."
A drive-up canopy will support an oval drive at the outpatient
facility's entrance. Portions of the drive will actually run
beneath the structure of the second floor.
Other work outside the facility included the construction
of about 50,000 sq. ft. of new concrete parking lot, all of
which was completed prior to construction to accommodate patients
and workers.
Once the outpatient facility is finished in April, extensive
renovations of the existing hospital's medical records area
will begin.
Gene Spillman, construction administrator with the hospital,
said the first floor renovations will convert the existing
medical records area into offices and various storage rooms.
"An area covering about 35,000 sq. ft. is being completely
gutted, re-designed and reconstructed," Spillman said.
"The renovations will also convert areas that had previously
served as outpatient services into expansions of existing
departments."
A significant amount of interior demolition will occur during
the process, with renovations complete by the end of 2004.
Upon completion, the new 65,000-sq.-ft. addition will support
several operating rooms, some procedure rooms, several treatment
rooms and an Intensive Care Unit. Radiation treatment rooms
will be encased with lead-lined sheet rock.
"We'll probably average anywhere from 50 to 80 crewmen
throughout much of the project," Riche said.
|