|
Centroplex adds exhibition hall
Pre-assembled truss spans lifted to support exhibition
hall roof
By Sam Barnes
The most critical component of the 205,000-sq.-ft. exhibition
hall and plaza at the Baton Rouge Centroplex will be completed
this summer, when the last of 16 steel truss spans are placed
as support for the new exhibition hall roof.
Steel fabricator Steel Service Corp. and erector Bracken Construction
Co. Inc., both of Jackson, Miss., fabricated and placed the
steel trusses, which reach as long as 210 ft.
The $30 million project, to be completed by January 2005,
is being built by Carothers Construction Inc., Water Valley,
Miss., and designed by Post Architects/Washer Hill & Lipscomb
of Baton Rouge.
Darryl Ballard, project manager with Steel Service Corp.,
said more than 1,800 tons of steel are going into the trusses.
"An assembly area for the trusses was virtually nonexistent,"
Ballard added. "We had to haul them to the site in sections
averaging 40 to 60 ft. long and 18 ft. wide." To prevent
unforeseen problems at the site, the Steel Service Corp. crew
completely assembled the steel trusses at the fabrication
shop, then disassembled them for shipment.
"It's a required specification, because in a structure
of this size and complexity, you're dealing with two different
worlds," Ballard added. "There is the math world
and the real world. There are a lot of things that can go
wrong that don't necessarily show up on paper."
Once the steel arrived at the site, Bracken placed the truss
sections on the ground in the approximate location of where
they were to be installed. Workers then completely assembled
each truss.
Three to five cranes were used to lift, place and bolt down
each assembled truss section on top of 43-ft.-tall concrete
columns. The entire process took three to four days.
"Under ideal conditions, we could erect about two trusses
a week, but with the inclement weather we've been lucky to
average just one," Ballard said. During such a delicate
operation, either rain or wind can create an unsafe environment
for a steel erector.
"If we're not careful, we could have a disaster on our
hands. We don't want the wind grabbing the truss when we're
trying to lift it." The steel trusses over the exhibition
hall are painted white because they will be exposed within
the hall.
Gary Lambert, project manager with Carothers Construction,
said the discovery of numerous unexpected underground obstructions
threw a "monkey wrench" into the project's critical
path from the beginning.
"There was every kind of underground obstruction you
could think of," he said. "We've hit old parts of
a railroad track foundation, building foundations and numerous
underground storage tanks.
"The storage tanks were totally unexpected."
When Carothers workers discovered each tank, they immediately
notified the city, which dispatched environmental contractors
to remove it and remediate the area.
"There were five different times that we had to go through
that process, the first in October and the last in late April,"
Lambert said. When the unavoidable delays occurred, some quick
thinking was necessary to rearrange the schedule so that work
could continue. Ultimately, about two weeks of time was lost.
Lambert said other early work included driving precast concrete
piles for foundation, demolishing surrounding facilities for
expansions and tie-ins, and relocating utilities.
Demolition required the use of high pressure water to expose
reinforcing steel at the Centroplex's existing plaza level
to allow connections to the new facility.
"We had to hydroblast the concrete away to expose all
of the reinforcing steel for the slabs and columns to tie
into the existing structures," he added. The hydroblasting
process proved faster and less damaging to the rebar.
By leaving an existing parking lot in place, the crew was
able to use it as a "working slab" during the driving
of 320 precast concrete piles as the foundation for the exhibition
hall. The parking lot will be completely removed once the
exhibition hall roof is completed and overhead work has been
done.
The 14-in.-sq., 130-ft.-long spliced piles were supplied by
Boykin Bros. Inc. of Baton Rouge and driven by Kostmayer Construction
Inc. of Metairie.
"The underground obstructions delayed the pile driving
quite a bit," Lambert said. "We met with the architect
and the owner and decided it would be best if we performed
some pre-excavation ahead of the pile driver to detect the
obstructions ahead of time."
Anywhere from one to 10 piles were driven for each pile cap,
which provide support for the exhibition hall's perimeter
columns.
Lambert said project sequencing has presented another logistical
dilemma for the contractor.
"Originally, we had 19 phases on this job," he added.
"We simplified that by combining operations and rearranging
the schedule to shave it down to seven phases."
Much of the sequencing is necessary during concrete placement
for the building's floor slabs.
"There's one section near the Centroplex at the plaza
level where the trusses are cantilevered, and when the trusses
from the exhibition hall tie into it, it will raise the cantilevered
section by about 3.5 in.," Lambert said. "We've
had to sequence our concrete pours accordingly."
Project sequencing was also necessary to accommodate existing
Centroplex operations.
"We're revamping the existing concessions areas, and
adding new concessions and ticket booth facilities, so all
those things had to be coordinated with the Centroplex,"
Lambert added. "The phases were arranged around their
schedule and their seasons so the disruptions could be minimized."
Once steel erection has been completed this summer, Roof Technologies
Inc. of Harvey will begin installing a standing seam metal
and modified bitumen roof system. Beginning at about the same
time, an extensive mechanical phase will require the installation
of a new chiller within the Centroplex's existing central
plant and the installation of a significant amount of ductwork.
Inside the building, architectural concrete blocks will go
up 14 ft. in the exhibit hall area as the primary wall finish,
whilie the entry lobby will be glassed in.
Lambert said the new structure will have an exterior architectrural
precast concrete and stucco finish, although the south wall
will have a brick finish. In the northwest corner of the building,
a large overhead door will allow tractor-trailers to drive
directly onto the exhibit hall floor.
Lisa Nice, project architect with Post Architects, said the
building's entranceway will be particularly impressive, supported
by a concrete column and beam system instead of steel trusses.
She added that each beam requires 60,000 lbs. of concrete.
"It (the entrance lobby) will basically be a tall open
space," Nice said. "The lobby will be carpeted,
but there will also be some terrazzo and granite interspersed
throughout.
"At the plaza level, there will be meeting rooms and
a nice public area. It physically connects to the existing
facility, so you'll be able to walk out of this building straight
into the existing Centroplex." Three meeting rooms in
the plaza area measure 60 ft. by 50 ft., 54 ft. by 50 ft.
and 60 ft. by 120 ft., and can each be subdivided to create
smaller meeting spaces.
The largest meeting room overlooks the exhibition hall through
a glass wall.
When the new exhibition hall and plaze level opens, the Centroplex
will have the luxury of having its first client already under
contract. A professional bowling organization recently agreed
to sponsor its annual tournaments in the facility from January
to July.
|