|
Concrete shapes a city
New administration building wedged into Gretna complex
By Sam Barnes
The cityscape of Gretna, across the Mississippi River from
New Orleans, has changed rapidly during the last few years,
as city, parish and state officials attempt to put a new face
on the government complex there.
The latest addition - a new $16 million, six-floor Jefferson
Parish Administration Building - is now rising within a tightly
congested area comprised mostly of buildings younger than
five years in age. Most notably, a Fifth Circuit Court of
Appeals building and a new district attorney's office building
border the site.
Brice Building Co. Inc., Metairie, began constructing the
six-floor administration building in August 2002 and expects
to place nearly 8,000 cu. yds of concrete before its completion
in mid 2004. A small section of the building to connect to
a district attorney's office building will be built with structural
steel.
Sizeler Architects, New Orleans, designed the structure.
According to Frank Milazzo, Brice jobsite superintendent,
the post-tensioned concrete building rests on a network of
spliced concrete piles that reach 130 ft. in length.
"Before pile driving could begin, we had to remove about
3 ft. of unsuitable soil, then come back with 3 ft. of new
fill," Milazzo pointed out. During the excavation, the
Brice crew uncovered several footings from an old Ford engine
assembly plant that had to be demolished and hauled away.
The stripping operation also encountered weather-related
problems, when heavy rains swamped the site during two separate
hurricanes last Fall.
"I think in two weeks we got nearly 40 in. of rain,"
Milazzo said. "When it happened, we just pumped the water
and continued on."
More than 200 14-in.-sq. concrete piles were driven in 65-ft.
sections and spliced by Kostmayer Construction Inc., Metairie.
The company drove an additional 110 12-in.-dia. pipe piles
to support the steel portions of the building. The concrete-filled
piles reach 130 ft. deep.
Crews then excavated 7 ft. below the piles from the finished
elevation and poured piles caps that range from 9 ft. by 9
ft. to 14 ft. by 11 ft.
After Brice poured 5,000 psi concrete for the building's
6-in.-thick first floor slab, a crew with CECO Concrete Construction,
Metairie, initiated a large-scale shoring and forming operation
for the elevated slab pours.
All of the elevated slabs contain both reinforcing steel
and post-tensioning cables tensioned to 33,000 pounds.
Concrete for the elevated slabs contains super plasticizer
to accelerate the setting times.
"By accelerating the times, we've been able to achieve
75 percent of strength much faster, which allows the tensioning
of the cables to begin earlier (performed by South Steel Erectors
Inc., Franklinton)," he said.
CECO is breaking down the shoring three floors below the
concrete operation.
"We've got to have three floors of shoring in before
we can strip the flooring, so the first floor shoring was
removed after the fourth floor was poured," Milazzo said.
The crew reached the fourth floor milestone in late March,
thus allowing mechanical, electrical, sprinkler and drywall
contractors to move into the building to begin work.
To accommodate the heavy downtown Gretna traffic, virtually
all of the concrete pours have occurred from 3-9 a.m.
"All of the concrete is being pumped from the ground,"
he said. One lane of an adjacent one-way street is closed
during the pours, then reopened by mid morning once the pours
are complete.
According to project manager Pat Descant, the pours are typically
performed on Fridays, allowing ample time for the concrete
to set and for the erection of shoring and forms to catch
up.
"We're then ready by week's end for concrete to be poured
for the next section," Descant said.
"We've broken it up into equal stages," Milazzo
explained. "On the first floor there were four separate
pours, for the second and third we had three pours, and from
the fourth to the roof we have two pours."
The floors in the steel section of the building were to be
poured in late Spring. "We'll pour that on top of metal
decking," Milazzo said.
The floor slabs vary in thickness from a minimum of 4.5 in.
to a maximum of 8 in. in areas to support mechanical air handling
units. Lafarge is supplying all of the concrete for the project.
"We're currently averaging about 10,000 sq. ft. of concrete
placement a week," Milazzo pointed out.
When construction of the building's exterior begins this
summer, the Brice crew will erect brick, curtainwalls and
windows on the south and west sides of the building, and glass,
window walls, brick and precast stone on the east, or main
entrance, side. The north side will physically connect to
the district attorney's office building.
"The east side is about 50-50 precast and window walls.
The precast bands run across the building," Milazzo said.
Roof work should begin this month, and will be made of a built-up,
two-ply, bitumen system.
Upon completion next year, the administration building will
have 80-ft. by 75-ft. council chambers, along with numerous
council and parish offices.
"The lobby area will be an open, glassed in area with
a semi-spiral staircase and terrazzo flooring," Milazzo
said. Mechanical and electrical work is being performed by
Towers Mechanical Contractors Inc., Westwego; and Heritage
Electrical Co. Inc., Gretna, respectively.
"The steel section of the building will support the
building's entranceway off the main road, and will physically
connect to the DA's building," he continued.
Access to the district attorney's building will be located
at the first floor only.
|