|
Necessary upgrades
Projects at two Shreveport plants
will boost capacity, improve efficiency
By Karla Wall
Upgrade projects have been underway since May 2005 at two
Shreveport wastewater treatment facilities. The projects,
under a single $22.3 million contract, will be completed by
May.
Upgrades at the Lucas plant are being done to increase the
capacity of the facility, said Barbara Featherston, project
engineer with CDM of Shreveport.
"The plant was built in the late 1970s, and while there
have been a few modifications made over the years, nothing
has been done to increase the plant's capacity," Featherston
said. The upgrades will allow the plant to meet the demands
of the increased population in the area.
The North Regional plant projects are geared toward improving
efficiency.
"The process just wasn't keeping up with the demand,"
Featherston added. "There were inflow problems in wet
weather." The plant is in a low-lying area.
The North Regional project includes the addition of a high-rate
clarifier, said Bernie Isom, project manager with primary
contractor Max Foote Construction of Shreveport. The 61- by
64- by 25-ft.-deep concrete tank is constructed of 4,000-psi
concrete and sunk 10 ft. into the ground, Isom said.
About 3,600 cu. yds. of concrete were used for both facilities,
Isom said.
Roughly 12,000 cu. yds. of dirt were removed at the North
Regional facility to make way for the new additions, which
also include a diversion box to divert flow during wet weather.
The tank is 16 by 16 by 20 ft. deep and is also formed with
4,000-psi concrete.
An influent pump station is also being added that will include
three 75-hp vertical turbine pumps from Fairbanks Morse of
Beloit, Wis. Ductile iron piping measuring 48 in. diameter
will take flow from the pump station to the new clarifier,
Isom said.
He said about 6,000 ft. of ductile piping furnished by C
& B Piping of Birmingham, Ala., were necessary for the
project, including 36-in., 42-in. and 48-in. pipe. Piping
is routed mainly underground at depths of 3 to 20 ft. throughout
the plant. Exposed pipe at the pump station is routed 12 ft.
above ground on concrete or steel supports.
About 10,000 sq. ft. of concrete roadway was removed to install
the new piping, Isom said. Road excavation was handled in-house.
Ventilation and exhaust systems for administration and equipment
buildings are also being installed at the North Regional Plant
by Thermo-Technics of Shreveport. Raymond Hill of Thermo-Technics
said the systems heat outside air to keep temperatures stable.
Specially-coated "hazardous duty" 10 kw electric
heaters from Trane are being installed, Hill said. Coated
with an epoxy-like substance, the heaters are less prone to
corrosion, a problem in North Regional's damp environment.
Heaters are wall- or ceiling-mounted. Ductwork for cooling
and heating systems is aluminum, also to prevent corrosion.
Exhaust fans for the North Regional project are roughly 30
in. by 30 in. by 3 ft. tall. The fans move 3,600 cu. ft. of
air per minute.
Electrical work at North Regional includes the installation
of a dual-feed supply system with an automatic back-up for
each system and each piece of equipment at the facility, said
Kevin Johnson of Feazel Electrical Contracting of Shreveport,
electrical subcontractor.
Power is routed through a 15-kw substation building to 16
localized transformers that bring the power down to 480 watts,
Johnson said. Power is distributed through across-the-line
starters and variable frequency drivers. About 20,000 ft.
of 15-kw cable is routed 36 in. below grade in concrete duct
bank.
A new automated control system includes programmable logic
controllers at each equipment site and connected in a looped
network. A local computer controls the network from the administration
building. The computer, using MMI software, provides operators
with a diagram rather than warning lights, Johnson said. About
18,000 ft. of fiberoptic cable was used.
The Lucas project requires the addition of a concrete high-rate
clarifier tank as well as new air conditioning, ventilation
and de-humidifying systems.
Hill said the environment at Lucas is reactive to most metals,
so ductwork is also aluminum.
|