|
High-tech treatments
Water, wastewater facilities use
technology to do more with less
By Chip Taulbee
A wide array of new technologies are being used in water
and wastewater treatment plant upgrades across the south central
region to make the water cleaner and the facilities' aroma
rosier.
The O.B. Curtis Water Treatment Plant in Ridgeland, Miss.,
and the Five Mile Creek Wastewater Treatment Plant in Birmingham,
Ala., will use ultraviolet rays for disinfection. Also, the
Ridgeland plant will be the first immersed membrane plant
in Mississippi treating surface water.
Contractors are also finding out these upgrades can get tricky
if the facilities are old and their drawings not always exact.
As general contractor Brasfield & Gorrie LLC of Birmingham,
Ala., can attest, the upgrades are always easier when you
are the contractor who built it in the first place.
O.B. Curtis Water Treatment Plant,
Ridgeland, Miss. Brasfield & Gorrie began a $42.7
million expansion in April on the Ridgeland water treatment
plant it originally built in 1989.
Fortunately, the owner - the city of Jackson - anticipated
the expansion.
"When we built the original job, a lot of the work we
did there was made to accommodate or facilitate this type
of an upgrade," said Brasfield & Gorrie project manager
Scott Sheumaker.
The addition of a submerged membrane filtration system will
double the plant's capacity to 50 million gallons per day.
Brasfield & Gorrie will also make modifications to the
plant's existing deep-bed filter system. The job includes
enclosing the high-service pump station, a block building
with a structural steel frame and adding another enclosed
high service pump station.
The project, not a particularly large concrete job for a
treatment plant, will include about 16,400 cu. yds. of concrete.
There will be plenty of new piping, however. The job calls
for about 2 mi. of ductile iron yard pipe and 8.5 mi. of small-diameter
pipe.
The plant will also get more than 70 new pumps of various
sizes, some with as much as 800 hp.
The project is a joint venture with Dixon Interior Finishings
of Jackson, Miss., and will be completed in December.
Central Wastewater Treatment Plant
Biosolids Management Facility, Nashville. Archer-Western
Contractors Ltd. of Atlanta began work in November on Nashville's
$117 million biosolids management facility at the Central
Wastewater Treatment Plant, which will be complete in three
years.
The new facility will turn solid waste into a pellet fertilizing
product "and all but eliminate the odor source from the
facility," Archer-Western project manager Kelley Hadley
said.
Archer-Western, who was contracted by Nashville's Central
Water Services for the design-build project, has hired the
local architecture firm Barge, Wagner, Sumner & Cannon
Inc. to research the surrounding historical Germantown area
and find matching brick colors and other features for the
facility.
Running adjacent to the eight-acre site will be a biking
and walking trail dotted with trees and other greenery.
So far, Archer-Western has removed countless buried bricks
at the site, which were part of a brick manufacturing plant
that once stood there. The new facility is going to primarily
be constructed on a foundation of H-piles driven into the
bedrock.
The project will include four dissolved air-flotation thickeners
along with associated control buildings; five digesters with
an associated control room building; and a 50,000-sq.-ft.
biosolids drying facility, which is the largest structure
onsite.
Archer-Western will use primarily concrete slabs-on-grade
with a structural steel skeleton and precast panels with built-up
roofing, except for an administration building that connects
to the drying facility, which will have a standing seam roof
structure.
Dry Creek Wastewater Treatment
Plant, Nashville. Four engineers designed the Nashville,
Tenn., treatment plant's upgrades as four separate jobs. Instead,
but Brasfield & Gorrie got the $38.1 million bid for the
whole project.
The contractor began work on the plant in July. Upgrades
are being made on solids handling, odor control, aeration
basin improvements and influent pumping.
"This is a large process mechanical job in that there
are a lot of pumps, pipes, mixers," Brasfield & Gorrie's
Scott Sheumaker said, citing about 315,000 lbs. of flanged
ductile iron pipe on the project.
The plant's old aeration systems and basins are being replaced
with diffuser equipment and floating aerators. The plant will
also get a new wet-weather pumping station with two 250-hp
pumps.
Most of the job's 7,300 cu. yds. of concrete will go into
a new digester complex. The plant will also have its existing
dewatering facilities refurbished. And new biofilters will
treat odors from around the site.
The four-part project was designed by Black and Veatch of
Overland Park, Kan.; Brown and Caldwell of Walnut Creek, Calif.;
Jordan, Jones & Goulding of Norcross, Ga.; and Jacobs
Engineering Group Inc. of Pasadena, Calif.
Five Mile Creek Wastewater Treatment
Plant Upgrade, Birmingham, Ala. Local contractor B.L.
Harbert International began work in July on the $52.4 million
upgrade on the Five Mile Creek Wastewater Treatment Plant
in Birmingham, Ala.
Once the project is complete in July 2008, the decades-old
plant will have boosted its capacity from 20 million gallons
per day to 30 MDG and peak flow capacity of 45 MGD to 70 MGD.
The plant, which now uses chlorination as a final phase of
treatment before the effluent goes into the creek, will use
ultraviolet rays as the last line of defense.
A new system control acquisition and data system will allow
the plant to be operated through computers that can open and
close valves and monitor and make other adjustments throughout
the treatment process.
Excavating a hole 50 ft. deep for the new combined headworks
and pumping station facility was tricky.
"Since we're in the existing plant the blasting charge
has had to be reduced somewhat," Lee said. "And
the rock was so hard that some of the rock had to be blasted
three and four times to get it to fracture so that we could
remove it."
The upgrade also includes two new clarifiers, a new aeration
basin, a new holding basin and new sludge drying beds.
Grand Prairie Pumping Station,
DeValls Bluff, Ark. Arkansas' Alluvial Aquifer has
been going down for years and if something is not done it
will be commercially useless by 2015.
So the U.S. Army Corps of Engineers contracted Granite Construction
Co. of Lewisville, Texas, to build a pumping station in DeValls
Bluff that will not only save the aquifer but also save the
area's farming.
Corps officials said the project will use excess surface
water and water from the White River to supplement a network
of on-farm tailwater recovery systems. The systems will also
fill on-farm reservoirs that store the water, which will also
provide some irrigation.
A six-pump, electric pumping station will move the water
from the White River. Granite Construction began work on the
station last June and should finish in December 2007 or January
2008.
The $34.9 million station will pump 1,600 cu. ft. per second.
|