|
Acadia Parish prison
New jail, sheriff's offices likely
to open in November
By Karla Wall
Though delayed a month by Hurricane Rita, work is now underway
on the Acadia Parish Prision facility in Crowley, and is expected
to be completed by November.
Lewing Construction of Crowley began work on the new 4-acre
complex in October. The facility will include a 23,000-sq.-ft.
jail unit and a 17,000-sq.-ft. administration building that
will house a training room, break room and office space for
the Acadia Parish Sheriff's Dept. It will also include recreation
and mechanical yards.
Lewing removed 300 cu. yds. of topsoil for the two buildings,
said project manager Joel Hebert. Roughly 500 cu. yds. of
compact clay fill was added for the bedding, supplied by LaCroix
Trucking Inc. of Rayne. The foundation for the jail unit consists
of 700 cu. yds. of concrete.
Lewing is using 3,000-psi concrete for below-grade footing
and 4,000-psi for the slab-on-grade, Hebert said.
The exterior of the 12-ft.-high jail unit will consist of
a pre-engineered metal structure overlayed with about 9 ft.
of CMU supplied by Southern Louisiana Masonry of Baton Rouge.
The remaining 3 ft. will be metal sidewall and will be installed
by J. Reed Erectors of Baton Rouge. The interior of the jail
will be formed with 8-in. solid fill CMU blocks.
The jail has been designed with central control and management
in mind, said designer Mark LaLande of Mark LaLande Architects,
Lafayette. Six 20-man dormitories and five four-man dormitories
will surround a control room through which guards will operate
all locks, plumbing and low-voltage electrical wiring using
touchscreen access and camera surveillance.
"We focused on managing the facility with maximum efficiency
using minimum staff," Lalande said.
The facility will also house a women's dorm, a medical isolation
dorm and a visitation room. The jail will be equipped with
cameras and computer technology that will allow teleconferencing
of arraignments, making prisoner trips to the courtroom unneccessary.
Arraignments will be held via wide-area-network links between
the courthouse and jail.
Plumbing has been roughed in for the jail unit, said David
Moulis with Moulis Plumbing Inc. of Lafayette. About 4,000
ft. of pipe was used for the sewer systems, Moulis added.
Pipe measuring 6-in.-diameter is being placed for the building
sewer and 8-in. piping for the sanitary sewer will be routed
from an existing manhole to two new manholes.
The 100 to 150 plumbing fixtures in the jail facility will
be stainless steel and tamper-proof.
"They'll be difficult to damage and difficult to make
malfunction," Hebert said. "If someone tries to
flush something down one of the toilets like a shirt or a
towel a fence valve stops it in the line before it gets into
the sewer system."
Hebert added fixtures are well-concealed, with mechanical
and electrical piping, wiring and devices located in a chase
area behind each fixture.
The administration building will consist of CMU, metal and
brick veneer. The structure will be framed by 2-by-4 and 2-by-6
metal studs supplied and erected by J. Reed. Flooring will
consist of commercial tile, carpeting in the office areas
and ceramic tile.
Hebert and LaLonde said the major challenge in the project
has been the weather. In addition to the hurricane delay,
frequent rain has made construction work difficult.
In December, the project was about a week behind schedule.
"It's rained at least a couple of days a week and we're
trying desperately right now just to get the foundation poured,"
Hebert said.
|