|
In the storm's wake
Harrah's Poydras Street Hotel relies
on ready-mix, precast to erect structure
By Angelle Bergeron
The $100 million Harrah's Poydras Street Hotel in New Orleans
was on the fast track to be completed by March.
"We poured the core mat at the end of October and were
at 27 floors, pouring the roof by the end of August,"
said Chris Watermeier, project manager for Broadmoor LLC,
one of the subcontractors on the job. "I'd say that's
pretty fast-paced."
Then Katrina came to town.
For the most part, the building fared the storm rather well,
but the contractor's original completion date has been pushed
back to Aug. 31.
"That includes not only missed days but also removing
and replacing what was damaged," said Jeff Blanchard,
project manger for NOW2, the joint venture comprised of New
Orleans-area contractors Carl E. Woodward and Walton Construction.
The only damage suffered by what owners specifically planned
to be an airtight and moisture-resistant structure was insulation,
water-resistant sheetrock and the specially designed exterior
cladding.
Broadmoor's $30 million contract to NOW2 includes the steel
superstructure, concrete work and design-build plan for the
GFRC and curtainwall/window exterior cladding system. Broadmoor
tested its exterior cladding system design by constructing
a three-story mock-up test wall at Construction Research Laboratories
Inc. in Miami, Fla.
"Then we put it through both positive and negative pressure
water tests," Watermeier said. "That was done to
ensure that no water would get into the system and the system
would withstand storm debris and wind."
In another attempt to ensure the system would meet the stringent
design specifications, Broadmoor even hired an engineer with
GFRC, who worked hand-in-hand with the structural engineer,
Jon Sofranko at Morphy Makofsky of New Orleans.
When Katrina hit, Broadmoor was about 90% complete with its
portion of the job, having installed glass up to the 20th
floor and GFRC almost through the entire 24th.
Only one panel fell off of the building (inside the site)
during the storm, but Broadmoor opted to replace all of the
panels on the top four floors rather than invest the time
and money in extensive testing.
"They were exposed to stresses they weren't designed
for," Watermeier said. "The panels were designed
for forces from outside to inside, but wind got in the building
and was pushing on the back side of the panels. Those panels
were not designed for that."
Broadmoor also replaced 30 panels that were on site waiting
to be installed that took quite a beating.
Because owners had emphasized waterproofing the building,
a good portion of it was effectively sealed off, Watermeier
said. "NOW2 had some moisture consultants come in and
(per their advice) the contractor replaced all the insulation
and sheetrock down on the north path of the building,"
he said.
Construction began back in April 2004 when Broadmoor demolished
a two-story structure on South Peters Street and began excavation
in preparation for the hotel's core mat foundation.
"First we drove sheeting and enclosed the entire hole
(109 by 175 ft.), then dug about 4.5 ft. to remove the old
footings, backfilled with sand and began driving pilings,"
said Joseph Gioe, vice president of field operations and field
supervisor for Broadmoor. The 220-ft.-long, 285-ton capacity,
20-in. pipe piles had to be driven in two, 110-ft. segments.
"We had to put them on steerable dollies to get into
the site," Gioe said. NOW2 was required to preserve a
nearby three-story historic structure that would serve as
the low-rise portion of the completed hotel.
"When we were digging footings for the new tower, the
common wall between the tower and the existing building was
moving, so Broadmoor secured it with steel reinforcing,"
Watermeier said.
Broadmoor then excavated the tower footprint to 17 ft. below
street level, poured a dry bottom and the pile cap - requiring
2,700 yds. of concrete - for the core mat foundation. The
pour lasted from 7 p.m. on a Friday to 4 a.m. Saturday.
"For the first part of the mix, we used super plasticizer,
which makes the mix flowable around a significant amount of
re-steel," Gioe said. The rest was a standard, pumpable
mix.
Broadmoor used a 6,000- to 5,000-pound high early mix, a
special form system and completed each of the post tension
decks in two-part pours.
"The mix achieves its design strength quickly so we
can move on to another floor, and this is the first time this
form system has been used in this area," Watermeier said.
The rolling form system on castellated beams is commonly
used in Las Vegas, Gioe said. Basically, two "W"
sections are welded together to create a hollow 28-in. beam,
which is lighter and has more carrying capacity.
The system is set on key points. Then the rollers are bolted
into the structure's columns, which help bear the load all
the way down to the foundation, he said. "We had to upgrade
the cranes to carry the forms, which are 27 by 52 ft, weigh
between 20 and 24 thousand pounds," Gioe said.
Apart from the damage previously detailed by Watermeier,
the new hotel "didn't have a heck of a lot of damage,"
Blanchard said. NOW2 is working on the project "full
speed ahead," he added, averaging 350 workers on the
job daily.
"The thing that has kept us going is Harrah's has been
really instrumental in helping a lot of our subcontractors
with housing," Blanchard said. Temporary trailers on
site and vouchers for nearby hotel rooms are some of the accommodations
provided by the owner.
"Also, for about three months they provided breakfast
and lunch for all of the workers on site. They made it the
best environment possible, under the circumstances, for people
to work. Harrah's has been an unbelievable client to work
for. Not that many owners have the capability to do what they've
done."
|