|
Outlook: Transportation
Highway industry to see unprecedented
year
By Karla Wall
The Louisiana Dept. of Transportation's fiscal year 2005-2006
budget, approximately $1.3 billion, was planned before the
federal transportation bill was signed and before hurricanes
Katrina and Rita came ashore along the Gulf Coast.
DOTD public information officer Mark Lambert said those three
events will mean a significant increase in activity in highway
and infrastructure projects in what was already a record year.
"There will be competition for materials and workers,
but any contractor in Louisiana who wants to get in the game
will have a very busy year," Lambert said. "There's
lots of activity going on."
The new transportation bill, signed in August, went a long
way toward funding the long-awaited extension of I-49 from
Shreveport to the Arkansas border, roughly 36 mi., and from
Lafayette south to New Orleans.
The bill earmarks $200 million for the northern segment of
the project, with the state matching at $40 million. The total
cost of the project is estimated at $363 million.
The Lafayette to New Orleans segment, estimated at $865 million,
is funded at $51 million through the bill, with the state
matching $10.2 million.
"We didn't get quite enough earmarked to finish the
entire project, but we can get a good chunk of it done,"
Lambert said.
The bill also provides $28 million for widening La. Hwy.
28 from Fort Polk in Leesville to Alexandria, $3.1 million
for La. Hwy. 6 construction to connect I-49 to Toledo Bend,
and $5.4 million for a new I-49 exit at Natchitoches at the
Waterwell Gateway Corridor/La. 6.
DOTD will avoid diverting funds for planned construction
to reconstruction due to hurricanes Katrina and Rita.
"The obvious exception is that we will not complete
planned repaving projects on damaged highways that will need
to be reconstructed," Lambert said.
DOTD has requested $165 million from the federal government
for immediate repair needs and $650 million for widening of
the heavily-congested sections of I-10 and I-12 in Baton Rouge,
which is now the staging area for the New Orleans recovery
area.
"We've also requested funding for I-10 widening in Lafayette,"
Lambert added. These sections will be widened from four lanes
to six.
Lambert said the state's largest upcoming project - a $200
million, three-phase project to construct an 18-mi. bridge
to replace the section of La. 1 from Golden Meadow to Port
Fourchon - will be let early this year.
Following are some of the larger highway projects currently
under construction in the state.
U.S. Hwy. 165, Grayson-Columbia.
Denton-James of Baton Rouge is overseeing this project to
reconstruct four miles of U.S. Hwy. 165. The project will
widen the highway from four to six lanes.
Existing roadway will be replaced with concrete paving on
a crushed stone base.
Denton-James operations manager Don Young said roughly 200,000
sq. yds. of concrete paving was used as well as 200,000 cu.
yds. of crushed stone base. Nine miles of 15- to 72-in. storm
drain pipe is being supplied by Rinker of Alexandria for the
project.
By far the most challenging aspect of the project has been
the relocation of utilities, which is being handled by ABMB
Consulting Engineers of Baton Rouge.
Project engineer Cindy Hall of ABMB said about 200 utility
poles had to be moved 60 ft. for the project to allow for
the 145-ft. right of way.
Several underground and line-based utilities also had to
be moved, including BellSouth lines, Atlas Energy gas lines,
CrossTex-LIG gas lines, Columbia Heights water liens, Village
of Grayson water lines and Town of Columbia water and gas
lines.
The project, started in September 2004, will be complete
in spring 2007.
Barksdale Interchange, Bossier
City. Work began in July on a project that will result
in a new 2,770-ft. overpass at the Shreveport-Barksdale interchange
with the Red River Bridge on Route La. 3032.
The new overpass will be supported by five 72-ft. spans,
with four 36-in. steel girders per span, said project manager
Chris Hughes.
Roughly 3,526 cu. yds. of concrete were used on the project,
according to DOTD spokesperson Darrell Goza. About 24,000
ft. of steel piles support 8,532 ft. of Type 3 girders and
4,940 ft. of steel girders. Anticipated completion is late
this year.
I-10, Causeway to 17th St. Canal,
New Orleans. Boh Bros. Construction of New Orleans
began construction on this $68.8 million project to widen
two overpasses in December, according to project manager Cameron
Johnson. The eastbound overpass will be widened from three
lanes to four and the westbound lane will be widened from
four lanes to five.
The overpasses will be re-paved and a new base will be added
using 75,000 tons of stone-stabilized base.
Roughly 134,000 cu. yds. of material was removed to make
way for new construction, said Boh Bros. operations manager
Jason Guy, and 143,000 cu. yds. of sand-based embankment was
brought in.
New piles, with footing and caps, will be erected for the
1-10 Causeway ramps, which will be constructed at a later
date. The project is scheduled for completion in 2009.
I-10, Coone Gully to La. 27.
This $42.4 million project, begun in June, will result in
the widening of 10 mi. of Interstate 10 from Sulphur to Vinton.
A lane and inside shoulder are being added in either direction,
said project manager Mark Dinnat of Diamond B Construction
in Alexandria, primary contractor for the project.
Roughly 450,000 cu. yds. of dirt from a borrow pit in Vinton
was brought in for the project, Dinnat said.
A soil/cement subgrade was added using 11,000 tons of cement
from Southwest Louisiana Cement in Moss Bluff.
About 75,000-80,000 tons of stone base was supplied from
Port Aggregates in Westlake and 360,000 tons of Superpave
asphalt manufactured on-site was used.
Besides a two-month delay due to hurricanes Katrina and Rita,
the major challenge of the project has been traffic diversion.
Dinnat said daytime and nighttime lane closures have been
implemented and concrete barriers will be utilized. Two lanes
will be left open in each direction. Completion is expected
in fall 2006.
Rigolets Pass Bridge, New Orleans.
Work is 20 percent complete on this $50.6 million project
by Massman Construction of Kansas City to replace a 3,200-ft.
swing-span bridge northeast of downtown New Orleans with a
72-ft.-high 5,400-ft. high-rise bridge.
The new bridge will be supported by 172 driven 66-in. precast
piles formed with 7,500-psi concrete and supplied by Gulf
Coast Pre-Stress in Pass Christian. Driving is 75-percent
complete, says Hayes. The bridge will have a concrete surface,
with ready-mix supplied by Harlow of New Orleans. Expected
completion is April '08.
|