|
Southwest Report
Despite
petrochemical downturn, region sees strong growth
By Karla Wall
Though high natural gas prices have forced an overall downturn
in the petrochemical industry, southwest Louisiana is experiencing
a period of heavy construction activity. And this growth is
expected to continue.
"This is a very good period for the southwest Louisiana
area," said Loren Scott, president of Loren Scott and
Associates Economic Consulting of Baton Rouge. "And that's
odd, because southwest Louisiana has the second-highest concentration
of chemical industry in the state, and the chemical industry
as a whole is not doing well right now."
Two major factors in the region's growth are continuing expansion
at the Citgo Lake Charles refinery and the planned construction
of five liquefied natural gas facilities in the area, each
totaling $600 million to $800 million. With two facilities
already underway in Hackberry and others in the permitting
stage, the area will see three to four years of construction
jobs from these projects, Scott said.
Citgo will begin construction on a $1.3 billion co-regeneration
project this summer and recently completed a $300 million
project that has allowed the plant to increase production
to 155,000 barrels per day, making it the fourth largest Citgo
refinery in the nation, Scott said.
The Lake Charles facility is also planning a $1.3 billion
project that will include a power plant, a 670 net-megawatt
integrated gasification combined cycle plant in Calcasieu
Parish; and will receive a decision soon on a possible $250
million diesel desulfurization plant.
"Citgo's going to more than offset the overall slump
in the chemical industry," Scott said.
The commercial and private sectors are also healthy, said
Scott Hines, Southwest Region president for the Louisiana
Association of General Contractors. "The private sector
is driving construction at an unprecedented rate, especially
in the retail, banking, lodging, restaurant and medical industries,"
Hines said. "We feel that 2005 is going to be a tremendous
>> year for construction."
Major projects include the $365 million d L'Auberge du Lac
Hotel and Casino, opening this month in Lake Charles, school
upgrades for the Calcasieu Parish School System, and several
construction projects planned for the Lafayette area, including
a $9.8 million road extension, a $6.7 million arts center
construction project, and the planned construction of the
$42 million Chateau de Leon Golf Course.
A federal highway bill recently approved by the U.S. House
of Representatives will mean additional funding for several
projects in the region, Hines added, including $13 million
for construction of an access road from I-210 to the Port
of Lake Charles and a bridge over Contraband Bayou in Lake
Charles; $5 million for improvements to the I-10 interchange
with Ryan Street in Lake Charles; and $30 million for projects
on I-49 and I-69 in the Lafayette area.
A downturn in the petrochemical industry isn't the only obstacle
to construction growth in the region, Hines said. Contractors
in all sectors have been faced with steel and concrete supply
shortages.
A more pressing concern, Hines said, is a shrinking labor
force.
"More and more contractors are having to do on-the-job
training," Hines added. "We don't have a big enough
qualified work force." The Incumbent Training Worker
Program, begun six years ago to give contractors easier access
to funding for training workers, has helped, Hines said, but
won't solve the problem.
"The state is trying to get a handle on the situation,"
Hines said.
Jennings Rehab Hospital
and Medical Office Building, Jennings. J. B. Mouton and Sons
Inc. of Lafayette began work in August 2004 on a $6 million
project involving a two-story medical office building and
senior care center and an elevated walkway connecting the
new building to the existing Jennings Rehab Hospital.
Despite weather delays and a steel supply shortage this past
summer, the project will be completed in June.
The new building will include an orthopedic surgeon's office
on the lower floor and a senior psychiatric care center on
the second floor. The care center, said project manager Danny
Eldridge, has required a few unique accommodations in the
construction process. To avoid having patients leave the facility
unattended or injure themselves, Eldridge said, the building's
ceiling is hard sheetrock rather than tile.
The supply grill for the HVAC is tamper-proofed and toilets
and other plumbing fixtures are bolted rather than screwed
into blocking.
"We finish one side of the wall, attach the fixtures,
then go to the other side and bolt them in with nuts, and
then finish that side of the wall," Eldridge said. The
windows are made of tempered glass.
The elevated walkway, consisting of steel framing and fireproofed
metal exterior, is being constructed with a standing seam
roof to improve wind resistance, Eldridge added.
Crews are working five to six 10-hour days each week to compensate
for delays, said Ronald Dugas of Mouton and Sons.
Hilton Garden Inn and Hotel, Lafayette.
Work began in November 2003 on a $12 million six-story
Hilton hotel located on the corner of Congress Street and
Cajundome Boulevard in Lafayette.
Complete with indoor pool and restaurant, the hotel will
house king and queen-sized rooms as well as suites. Fontaine
Construction of Youngsville has stepped up its work schedule
on the project, working weekends to compensate for >>
weather delays, said Hall Fontaine, project manager.
More than 200 30-ft.-deep drill shafts were required to create
the building's foundation, Fontaine said. The shafts were
shored up with more than $50,000 worth of rebar and 8-ft.-long
pile caps.
The indoor pool and hot tub were formed as part of the building's
foundation.
"It was just a matter of digging the pool inside the
main foundation, rather than outside," he added.
F.G. Mouton Hall, ULL, Lafayette.
BEO Contractors of Lafayette began work in January 2004 on
an $8.8 million construction and renovation project that has
created a new three-story business college building and will
eventually create a new look for an adjacent building.
The 65,000-sq.-ft. business building, now complete, houses
a 250-person lecture hall, classrooms, case presentation rooms,
offices and graduate study work labs.
Bringing up a three-story building in a 20-ft.-wide space
between buildings on a functioning campus proved a challenge,
said Gerald Favaloro of BEO.
"We had to coordinate deliveries so that materials were
delivered right when we needed them," Favaloro said.
"We had to use fencing and directional information to
handle student traffic flow. The university gave us plenty
of off-site storage, so that helped."
The project also required completion of the fiberoptic network
in the building. Each desk location in the lower-floor "smart"
classrooms is connected to the university information system
for in-class presentations. Data and voice ports for Internet
connection are also provided at each station.
"We ran fiberoptic cable from the main communications
center at the administration building and sub-routers coming
off of that to each station," Favaloro said. Installation
involved about 400 lin. ft. of aluminum cable trays, Favaloro
said.
An elevated open walkway of structural steel, precast and
poured-in-place concrete will connect the new building to
the existing building slated for renovation.
Work began on the renovation in January with asbestos abatement
on the structural beams on the first and second floors of
the existing building, said project superintendent Phillip
LaVergne of BEO. The building will house classrooms, seminar
rooms, offices and a computer lab. Work is expected to take
eight months, LaVergne said.
Once asbestos work is complete on the third floor, work will
begin to resurface and repaint sheetrock walls, re-wire the
building, change the duct work throughout the building, install
new entry doors and larger windows, and rewire the computer
lab on the first floor of the building.
LA 87 Spur, Iberia Parish.
Boh Brothers Construction of New Orleans is undertaking the
$13.3 million expansion of LA 87 in New Iberia to accommodate
new construction in the area, said Mohammed Borazjani, project
engineer with the Louisiana Deptartment of Transportation.
When complete, the project will have widened Hwy. 87 to three
lanes and added a four-lane vertical lift bridge providing
50 ft. of clearance across a bayou, replacing a swing span
bridge.
Piles have been driven for the project, said Ed Scheuermann
of Boh Brothers. The bridge will include two 90-ft. towers
on either side of the bayou.
Over half complete, with all of the substructure in place
on one end of the bayou, the project has been temporarily
halted to allow subcontractors to move utility lines that
are impeding work on the bridge. Borazjani expects that the
lines can be moved as early as mid-summer, and work will resume
on the bridge.
US 171 Four-Laning, Gillis to Longville.
R. E. Heidt of Westlake is taking on two projects to widen
US 171 from Gillis to Longville. The first project, spanning
9.15 mi. from Gillis to Ragley, will cost $17.4 million and
will be completed by December.
The second project, which will widen 6.27 mi. of the highway
from Ragley to Longville, will cost $11.9 million and will
be completed by mid-May.
Traffic diversion has been a major concern, said project
manager Brent Arabie, but has gone smoothly.
"We're just keeping traffic on the old part of the highway
while we're working on the new lane," Arabie said. "We
recently switched traffic on the east side to the new highway,
and we're now working on the west side, on the Ragley to Longville
project.
Weather delays have been a problem, said Arabie, and may
push back completion dates as much as two months. The company
also had to deal with a concrete shortage over the summer.
"Our supplier got their concrete from Mexico,"
he added. "The suppliers were having trouble getting
(cement) in. Demand was high and (the suppliers) couldn't
keep up with it."
US 171 Four-Laning, Longville-DeRidder.
A project that will four-lane and resurface 11 mi. of US 171
from Longville to DeRidder will be completed in March 2006.
Headed by James Construction Group of Baton Rouge, the project
began in April 2003 and involves constructing an extra lane
in each direction and resurfacing existing lanes.
Trinity Baptist Family Life Center,
Lake Charles. Alfred Palma Inc. of Lake Charles is
heading the $7 million construction of a new family center
for Trinity Life Baptist Church in Lake Charles. Begun in
October 2003 and now just weeks from completion, the 63,000-sq.-ft.
facility will house two gyms, fitness area, rock climbing
wall, an indoor playground, women's and men's locker rooms,
classroom areas, a running track and a >> 23-ft. by
25-ft. stage.
The building's size alone makes it unique, said James Palma,
project manager for Palma Construction.
"I don't know of any other building in the area with
dual gyms."
About 385 tons of structural steel, including 100-ft.-long
trusses and 16-in. by 12-in. tube steel, was used in framing
the building, Palma said. The framing was completed before
the steel shortage hit last summer.
"We were fortunate that we got it all through the shop
before the shortage hit," he added. "We had a window
of opportunity, with little time to spare." The metal
roof panels, however, were delayed due to the shortage.
About 40,000 sq. ft. of metal panels were used in the roof,
as well as 32,000 sq. ft. of 8-in. panels.
Useful Sources:
For more information about upcoming development in Lafayette,
go to:
http://www.lafchamber.org/site.php
For more information about upcoming development in Lake Charles,
go to:
http://www.chamberswla.org/
|