|
Stemming the tide
Projects
harness precipitation to prevent flooding
By Angelle Bergeron
In areas below sea level, flood control is an ever-present
element of public works construction.
From maintaining and upgrading existing drainage systems
to creating new structures, contractors are reaping the benefits
of projects designed to harness the New Orleans area's abundant
precipitation.
The U.S. Army Corps of Engineers maintains the lion's share
of such projects, albeit with a limited and sometimes unreliable
budget. The nearly $40 million Harvey Canal Sector Gate Complex
is making history as the largest current contract for the
corps and the only sector-gate system in the area designed
strictly for flood protection.
When complete, the gate will close only during a hurricane.
New Orleans-based Boh Bros. Construction began work in March
2004 on what was originally a $35.7 million contract to construct
a cast-in-place concrete foundation and 27-ft.-long wall system
to support two 25-ft.-tall, 170-ton steel gates.
The contractor is constructing huge cofferdams in the middle
of the canal. Once the water is pumped out, Boh will build
the structure in dry conditions 26 ft. below the surface of
the water under regular marine traffic.
Boh's contract also requires constructing floodwalls to tie
into the Cousins Street Pumping Station and provide one of
the final connecting links in the Corps' huge Westbank and
Vicinity New Orleans Hurricane Protection Project, said Carol
Burdine, senior project manager for the corps' New Orleans
District.
The Harvey Canal Sector Gate Complex is the gateway between
hurricane protection on the east side of the canal and the
existing Algiers levee system.
Originally scheduled for completion in December 2006, the
project has run into a few snags. Boh's original contract
called for constructing a temporary fender system to protect
the cofferdam and provide an 80-ft.-wide opening for marine
traffic.
The contract also stipulated that the system would be moved
twice during the project, but Boh had to re-design the fender
system to be moved twice a month and create a 100-ft. opening.
This resulted in a 40-day work extension, said Vincent Saladino,
Boh's project superintendent.
"Now the corps has postponed the start date for another
portion of the project, a concrete closure wall that we have
to build to tie into the Cousins Pumping Station," Saladino
added.
The corps awarded Texas-based AquaTerra Contracting Inc.
an $11 million contract for a portion of the Cousins Pump
Station Complex Discharge Channel, Flood Walls and Concrete
Culvert, said Stuart Waites, project manager for the corps.
"The work consists of the prefabrication and installation
of a 110-ft. by 126-ft. float-in concrete culvert structure
under the Lapalco Bridge in the Harvey Canal," Waites
said. AquaTerra's contract also includes channel excavation,
embankment work, riprap, constructing floodwalls and relocating
36-in.-diameter city water lines that were moved to accommodate
the discharge culvert.
"AquaTerra fabricated the culvert north of the project
at Bollinger's yard on the Canal, floated it to the Lapalco
Bridge, then flooded the chambers and sunk it into place,"
Waites said.
The contractor experienced what Waites referred to as "normal,
excusable" construction delays and is expected to complete
in April instead of the original contract date of June 2004.
Boh's contract, a portion of which has been hindered by AquaTerra's
late completion, has been modified to accommodate the delays,
he said.
Although Boh Bros.' contract is now approaching $40 million,
the contractor doesn't expect to receive more than $17 million
from the Corps this year, reflecting a general trend of funding
woes for anyone doing business with the Corps.
Patriot Street Canal. Belle
Chasse-based Circle Inc., contractor for the $12.2 million
Patriot Street Canal in Barataria, delayed construction on
that flood-control project several months until the corps
could pay up.
Awarded in Fall 2003, Circle's contract includes constructing
a concrete flume and slope paving along 3,700 lin. ft. of
an existing, man-made canal.
"We were scheduled to start work in December when there
were rumblings that the Corps of Engineers was running short
of funds," said Matt O'Brien, project manager for Circle.
The contractor spent September to December 2003 designing
the temporary restraining structure and then, after a nearly
$1 million outlay for sheet piles and cranes, it decided to
wait on the final budgetary decisions of the Corps.
"When they officially announced in February 2004 that
they weren't paying until October, we went to work and kind
of paced ourselves to alleviate delaying the start of the
job until October," O'Brien said.
Originally scheduled for completion in late October, the
deadline has been pushed to May 2006.
Although Circle continues to forge ahead, progress isn't
what the contractor anticipated.
"The TRS (temporary restraining system) is the horse
that drives the carriage," O'Brien said. "We wound
up using longer, heavier sheets and they are driving harder
and pulling harder than the soils reports would indicate."
Circle is working in 300-ft. sections, blocking the canal
with sand dams and then re-routing the flow of water. Because
the canal provides drainage for the surrounding community,
Circle must stop work and break their dams when there is any
substantial rainfall.
"When you break the dam and let the water flow through,
you have to go back and clean up, pump it out and you can
lose anywhere from three to 10 days every time," O'Brien
said.
So far, Circle has completed 1,200 of the total 3,700 ft.
of flume and remains on schedule in spite of 19 flood modifications
within a year, said John Messina, quality control. It's rather
ironic that water remains the biggest obstacle to completing
this particular flood-control project. "We're working
in the downhill side of water and the trick is always keeping
the water off of you," Messina said. "Even when
it's not raining, we are always working to keep water off
the site."
Working to staunch the constant flow of water with a slow,
tiny trickle of funds seems to be the norm for the corps.
The Patriot Street Canal project is one of approximately 40
contracts in Jefferson Parish funded through the Southeast
Louisiana Flood Control program, said Stephen Hinkamp, resident
engineer for the Corps' SELA Jefferson projects.
"There have been some budget problems for the past two
years and we've been delinquent," Hinkamp said. The Circle
contract is phone one and, although a phase two is on the
books there are no immediate plans to let the job due to lack
of funds, Hinkamp said.
"I can't promise anything on the budget and I can't
promise a May 2006 finish date for this phase because I can't
predict the rain," Hinkamp said.
Comite River Diversion Canal.
Keeping high and dry during construction has been the
primary concern of B&K Construction, the Mandeville-based
contractor awarded the $27.7 million Corps of Engineers Comite
River Diversion Canal project in September.
"We're building a control structure in a 100-ft.-deep
hole," said Blake Andrews, project manager for B&K.
"That's probably the biggest challenge, maintaining a
dry hole."
Before B&K mobilized on the site, James Construction
of Baton Rouge did some site clearing and excavation. B&K
is handling the second of 15 phases on the project, which
involves further excavation and construction of the Lilly
Bayou control structure, Andrews said. To complete the task,
B&K brought in a dewatering engineer, Marion Skouby, from
Missouri.
The engineer has designed many such systems and worked with
B&K on previous projects, Andrews said.
The 30-month project is the largest contract B&K has
ever handled and the contractor is purchasing and installing
a onsite concrete plant. B&K will also be digging a small
section of earthen channel on either side of the structure
and placing riprap.
The job is scheduled to be completed in February 2007 and
will reduce water levels in the Comite and Amite rivers.
Useful Source:
For more information about the New Orleans District, go to:
http://www.mvn.usace.army.mil/
|