|
Northeast Regional Report
Things are picking up in traditionally
stagnant area
By Martin Schwartz
Economic indicators are forecasting growth in northeast Louisiana
in the coming year, but area professionals are taking an "I'll-believe-it-when-I-see-it"
attitude.
In the 23rd edition of the Louisiana Economic Outlook, LSU
researchers Loren C. Scott and James A. Richardson and SLU
researcher A.M.M. Jamal are projecting more than 3,000 jobs
will be added in the region in the next two years.
Louisiana's smallest metropolitan statistical area is Alexandria,
but the city is expected to be the second-fastest-growing
MSA in the state thanks to the $100 million Union Tank Car
project and continuing projects at England Air Park.
Monroe remains the poorest performing MSA in the state with
the loss of 400 jobs from the closure of the city's State
Farm facility and claims center. Employment is expected to
increase only marginally in 2006.
But Miriam W. Russell, regional representative for Northeast
Louisiana Economic Development in Monroe, is optimistic about
several plans either in progress or being developed for the
area.
These include:
- The possible expansion of Pilgrim's Pride in Union Parish.
Pilgrim's Pride Corporation is the second-largest poultry
producer in the United States and is one of the largest
employers in the area.
- A Vineyard Furniture warehouse expansion in Franklin
Parish.
- The $68 million renovation of the Student Union Building
and construction of new student housing at the University
of Louisiana at Monroe. Louisiana Tech has similar projects
underway.
"We're working on several projects through economic
development >> agencies such as Ouachita Economic Development
Corporation and Northeast Louisiana Economic Alliance, which
handles the rural parishes outside of Ouachita Parish,"
Russell said, declining to name specific projects or price
tags.
Retail development also continues along the I-20 Economic
Corridor running parallel to the interstate from West Monroe
to Monroe.
"There's a private group that has bought some properties
in West Monroe that includes the old K-Mart building and they're
doing some development there," Russell said.
Project snapshots
Procter & Gamble liquid detergent
plant expansion, Pineville. Everything is on track
for an early spring opening of Procter and Gamble's $120 million
plant expansion in Pineville, said Bonnie Lemoine, P&G
public affairs coordinator.
Though production of liquid detergent will be underway, the
plant won't reach total completion until summer. It will be
one of only two liquid manufacturing plants in the country.
Work began in early 2003 and involved the largest continuous
concrete pours in P&G's history with more than 30,000
cu. yds. required for vessel and tank foundations. The vessels
themselves were largely fabricated offsite with only those
too large for transport fabricated on-site.
Fru-Con Construction Corp. of Ballwin, Mo., is the project's
construction manager; Inland Construction of Pineville is
the general contractor; and Lockwood-Greene Engineers of Spartainburg,
S. C., is the engineer. At the peak of construction, 800 workers
worked alongside P&G employees.
Utilizing Louisiana's Economic Development's business clustering
model, P&G has been able to attract front-end suppliers
to locate near the plant. Plastipak Packaging Inc. is building
a 500,000-sq.-ft. facility on 62 acres adjacent to P&G.
The $45 million facility will provide containers for P&G's
Heavy Duty Liquid (HDL) detergents and will employ more than
100 workers.
Union Tank Car plant, Alexandria.
Gov. Kathleen Blanco (D) was doggedly determined to
see that the Chicago-based Union Tank Car Company brought
its new plant to Louisiana. Code-named "Project U,"
Blanco refused to take no for an answer, even after it seemed
the project was bound for Texas.
The results became official in September 2004 when Blanco
and Union Tank Car officials signed a Cooperative Endeavor
Agreement to bring the $100 million, 850-employee plant to
Alexandria. The plant will encompass up to 1 million sq. ft.
adjacent to the England Industrial Air Park and Community
in Rapides Parish.
When fully operational in 2006, the plant will have the capacity
to produce as many as 70 tank cars per week. The Shaw Group
of Baton Rouge will provide design and engineering for the
project.
State and local incentives to bring the plant to Alexandria
have been valued at approximately $65 million, including more
than $30 million from the state for infrastructure improvements
and construction.
Federal medium-security prison,
Pollock. On 120 acres at the Federal Prison Camp in
Pollock, Memphis-based Flintco is engaged in a $93 million
project that is part construction, part manufacturing. The
new medium-security prison being built for the Federal Bureau
of Prisons (FBOP) will consist of 14 buildings using precast,
tilt-up walls and cells all fabricated on-site.
"We took about 20 acres down here for our cell casting
area," said Darryl Harris, construction manager. "Then
we did another 10 acres and put in a tilt-up wall manufacturing
plant." The on-site construction helps keep down transportation
costs on the design-build project that will vary in height
from one to six stories and will include special housing units,
kitchen, recreational facilities, power plant and administration
for the prison.
Harris said approximately 80,000 cu. yds. of concrete from
TXI will be used in the construction of walls and cells. An
average of 320 workers is on the job, including 26 subcontractors.
This is the >> company's third project for the FBOP.
The prison is on schedule for completion in July 2006.
U. S. Highway 165, Grayson to Columbia.
Clearing is completed and utility relocation is in
progress for the $25.6 million road widening and repair on
U. S. Highway 165 from Grayson to Columbia, said Don Young,
operations manager for Denton-James LLC of Baton Rouge. Work
started late last year with removal of underground storage
tanks and contaminated soil along the construction route.
Part of Louisiana DOTD's Transportation Infrastructure Model
for Economic Development, the project is just one part of
the widening of 162 mi. of U. S. 165 in 31 segments from I-10
to the Arkansas border.
Young said current work in the area is at a standstill while
relocation is in progress, but he expects to begin phase two
of the project on-schedule in March with a crew of about 60.
The project includes adding additional lanes and reconstructing
existing lanes to create 5.5 mi. of five lane roadway.
The road is essentially made of concrete with only a small
amount of asphalt transitions, Young said. About 60,000 cu.
yds. of concrete will be used in the road project that is
on target for a spring 2007 completion.
U. S. 165, Columbia. "A
snail's pace" is how project manager J. D. Steward describes
the current progress on $19.8 million project as workers await
utility relocation.
"We've got just a skeleton crew trying to work whenever
we can to get ahead of the game," he said.
Steward said his part of the project runs from the Ouachita
River a mile south and a quarter mile to the north, through
the city of Columbia and the approaches on either side of
the Ouachita River bridge.
"We've got about 1,700 ft. of approach including 10
drill shafts averaging 130 ft. deep and 10 ft. in diameter,"
he said.
What makes the project unique is the length of the bulb-t
girders being used in the approaches, some of which run 140
ft., 10 in.
"That's some of the longest bulb-T girders in the state,"
he said.
The first test pile was driven in February 2004, and Steward
said he expects the project to be completed on schedule in
early 2006. Jensen Construction Co. of Kansas City, Mo., is
the contractor for the project.
England Air Park terminal, Alexandria.
The Alexandria International Airport is getting a new
$23.9 million terminal at the former site of England Air force
Base in Alexandria. The two-story structure features 34,000
sq. ft. on the ground level with a "tug" area covered
in part by the 50,000-sq.-ft. second level.
The project broke ground in May with a scheduled completion
date of May 2006, and is a part of several planned phases
of expansion at the airport.
"We're doing Package Two," said Greg Corbett, project
manager for Ratcliff Construction of Alexandria. "Package
Three, which will be a separate project, will include the
parking lot and drive associated with the new terminal. Package
Four will be the airport side, the taxi way and places for
planes to park. We're not involved with those because those
plans are not out for bid yet."
The new terminal is being built with structural steel, metal
studs, brick veneer and window walls. The foundation consists
of wood pilings, pile caps and grade beams under a 6-in. floating
slab.
Health & Physical Education
Building, Grambling State University. Grambling State
University's President Neari Warner, speaking at its groundbreaking,
called the new $19 million Health, Physical Education and
Recreation (HPER) Building at Grambling State University "long
overdue."
Nat Mixon, project manager, said Ruston-based Lincoln Builders'
part of the project comes to about $16.5 million.
The structural steel building has some precast for the bleachers
and will have a brick and steel siding exterior. The 135,000
sq.-ft. structure will have a 96,000-sq.-ft. events level
and a 49,000-sq.-ft. second-floor concourse and will seat
7,500 for basketball games and up to 9,000 for non-sporting
events.
Mixon said the building required extensive cutting-in to
an existing hill on the campus to establish the ground floor.
"We had quite a few yards of dirt to move," he
said. "I'm not sure what the quantity was, but it required
four weeks of steady hauling."
The project is on target for a Spring 2006 completion.
US 167, Winnfield. An $18.6
million project to widen U. S. Highway 167 for 3 mi. in the
middle of the town has met with delays due to miscalculations
in some of the cross sections on the south side of the project.
"I just updated my schedule and we're about six weeks
behind, if we started today," said Bernie Sincavage,
project manager for James Construction Group. "We were
scheduled to be completed June 2006. Right now I'm projecting
August 2006."
And that's if work can get started soon.
The two- to four-lane conversion for the TIMED project started
out with no problems before hitting the snag in late Autumn
04. In addition to 100,000 sq. yds . of paving for the new
road, the project involves replacing a 1,000-ft. bridge that
crosses the railroad tracks in town and putting a smaller
bridge on the south end of the job to replace an existing
box culvert.
"We were able to proceed with the bridge construction,
in fact, we're a couple of weeks ahead," Sincavage said.
"I've made some suggestions to the state about putting
some temporary detours in so we could take traffic off the
old highway. We could possibly continue with our bridge construction
if we are able to put these temporary detours in."
But in the meantime, he said, his crew is waiting on the
engineers.
US 167, Ruston to Vienna.
Work is also progressing slowly on roadwork on US 167 from
Ruston to Vienna.
"We're not very far along," said David Huckbay,
project manager for James Construction Group. "November
killed us with all that rain we had."
But unlike the Winnfield project, work is progressing on
the $18.3 million project to build four miles of concrete
roadway on Highway 167. Three miles of that project will be
five lanes (four plus center turn lane) with a curb and gutter
and the last mile will be four lanes.
|