|
Environmental protection
ConocoPhillips installs desulfurization
unit at Lake Charles refinery
By Karla Wall
Mechanical construction is under way on a gasoline desulfurization
unit at ConocoPhillips' Lake Charles refinery. The new unit
will ultimately help the plant meet 2006 EPA gasoline sulfur
content regulations well ahead of schedule.
The facility, which will utilize ConocoPhillips' own "S
Zorb" sulfur removal technology, will be operational
in the fourth quarter and will enable the refinery to reduce
the gasoline pool sulfur content to 30 parts per million under
the new EPA regulations. The current average gasoline sulfur
content is 200 ppm.
This is the third S Zorb sulfur removal unit to be built
inside the ConocoPhillips refining system, with one more currently
planned.
The S Zorb technology utilizes a proprietary sorbent that
extracts sulfur from the gasoline. The process is unique in
that it can reduce sulfur levels to below 10 ppm without the
resulting loss of volume or octane that is associated with
other gasoline desulfurization processes.
The current work requires both Inside Battery Limits (ISBL)
and Outside Battery Limits (OSBL) construction.
Burns & McDonnell Engineering of Kansas City, Kan., and
Fluor Corp. of Pasadena, Calif., have been designing the OSBL
and ISBL work, respectively, for more than a year. Performance
Contractors of Baton Rouge was awarded the ISBL civil portion
of the project, as well as the ISBL and OSBL mechanical portions.
Burns & McDonnell is providing construction management.
Performance site manager Steve Stark said the project's greatest
obstacle has been coordinating the variety of machinery, equipment
and personnel in a limited space. A crew of about 225 will
be working at the site.
"We're in a congested area and there's a lot of activity
going on," Stark added. "It takes a lot of coordination
and communication." Weekly coordination meetings are
held with Burns & McDonnell and ConocoPhillips management.
The contractor must also work in an operating plant around
existing process equipment, process lines and machinery.
"We've had a very good relationship with Burns &
McDonnell and ConocoPhillips," Stark said. "They've
done a great job of communicating with us and keeping us informed
of plant activities that might affect our work activities."
Performance was provided with a schedule of the plant's shutdowns
so that work on the project could be coordinated with the
plant's shutdowns and turnarounds.
Safety is the top concern for Performance, Burns & McDonnell
and ConocoPhillips.
"We have daily safety meetings for Performance and weekly
safety meetings for ConocoPhillips," Stark added. "To
date, we've experienced zero recordable incidents and no lost
workdays, and our goal is to complete the project with this
same safety performance."
When the project began last summer, Performance removed existing
machinery and equipment from the site. Two areas measuring
125 ft. by 55 ft. and 215 ft. by 75 ft. were dug to depths
of 7.5 ft. and 4 ft., respectively, and about 3,000 cu. yds.
of soil were excavated. Existing concrete piles were demolished
using jackhammers and mini-trackhoes equipped with breakers.
About 315 auger cast pilings lined with reinforcing steel
were then installed as foundation.
"It was June, so the heat and humidity were major safety
concerns for our craftspeople working in the excavations,"
said Stark. "We went to extended breaks, we had rest
stations set up by the work locations and ConocoPhillips provided
water-cooled fans for the site."
Stark said the foundations and area paving were poured using
2,100 cu. yds. of concrete and more than 140 tons of rebar.
The ISBL portion of the project requires 580 tons of steel,
all erected by Performance with a 200-ton crawler crane to
lift equipment. Fireproofed steel columns used in the job
measure up to 20 ft. in length and weigh up to 10,000 lbs.
More than 110 pieces of equipment are being installed, including
a 123-ft.-tall reactor where the sulfur removal will take
place. The reactor was shipped by rail from Emporia, Kan.
Other installations include 23 new pumps to be used for various
processes, two new tanks, 24 shell and tube heat exchangers
to connect new and existing equipment, and a new flare stack.
About 85,000 ft. of pipe will be installed to link the ISBL
and OSBL portions of the project.
|