|
New Orleans revival
Seven structures restored,
consolidated into Country Inn & Suites
By Angelle Bergeron
Renovation projects always include some unknowns, but the
restoration and consolidation of several New Orleans historic
structures into the Country Inn & Suites by Carlson presented
an inordinate number of surprises.
Still, Brice Construction Co. of Metairie managed to complete
the $11.4 million project in time for the January grand opening
and create a first-of-its-kind product for the privately held
worldwide company.
Brice started demolition of the seven masonry structures,
all of which were built between 1850 and 1900, in December
2003. The buildings are situated in a U-configuration between
Magazine, Gravier, Picayune and Natchez streets in the Central
Business District in New Orleans.
The main entrance at 313/315 Magazine St. and one other building
were warehouses. The building at 523 Natchez St. was the former
home to the Clarion Herald, a local Catholic newspaper. The
three buildings to the rear, facing Picayune, were old warehouses
that had been most recently converted into condominiums.
Brice's contract included complete demolition of the interiors,
the addition of floors to five of the structures and construction
of a new, steel structure to connect the buildings at 523
Natchez and 323 Magazine.
That part of the project was, without a doubt, the most challenging,
said Mitch Melancon, project manager for Brice.
"We had plans, but nothing was exactly like it was in
the field," he added. Tying the structures together required
a tremendous amount of on-site modifications to make all the
elevations work with wood, concrete, steel and brick.
Due to foundation settling, the structure at 523 Natchez
was leaning about 18 in., but Brice had to salvage the exterior
walls so the owners could reap the benefits of historic tax
credits. The contractor built new base footings and a steel
skeleton that went to the roof of the four-story structure
and horizontally tied into each floor with steel joints and
straps.
"Everything had to be custom fabricated in the field
to make those floors meet," Melancon said. "Ninety
percent of this was done the only way you could do it, which
is in the field."
The demolition, in addition to the removal of numerous interior
walls, involved saw cutting about 100 openings. In the common
wall between 313 and 315 Magazine, 35 openings were cut to
create common areas in what would be the lobby and public
portions of the hotel.
"When we started cutting them open, we found major voids
between the bricks and grouting," Melancon said.
Architect John Campo said it was the first time in his 20
years of doing business in New Orleans that he had seen such
a thing.
Masonry walls are usually solid, three and four wythes thick,
said Campo, the president and CEO of John T. Campo & Associates
Inc. Architect/Planners. The concrete typically used in the
late 1800s often has up to three times the strength of concrete
required by today's standards.
"Apparently, when it was built, the mason decided not
to put mortar in those walls," Campo said. "It was
just loose-laid, and I don't know how they held up."
Masonry Solutions International of Maryland was selected
to handle the problem.
"They came in and drilled thousands of .5-in. holes,
8 in. on center, and blew out all the loose material with
water and compressed air," Melancon said. Once the walls
were clear of debris, the company pumped in a mortar that
binded to the existing brick and filled in the voids.
"When they were pumping it in, as soon as the fill started
shooting out they would plug up all of the holes," Melancon
added. "Then they came back a day or two later to patch
them."
Brice also discovered a 70-ft.-long wall with no footings
that unfortunately marked the location of elevator shafts,
steel supports tied into the roof and the main electrical
vault that was to house all of the electrical and plumbing
pass-throughs.
"That's what slowed us down," Melancon said. "We
were supposed to be finished by Dec. 15, but we got an extension
of 51 calendar days due to those structural deficiencies that
weren't evident in the design phase."
The repair required that the contractor dig out the footing
in 5-ft. increments to ensure the structural integrity of
that wall.
"We would go in and form, put in the concrete and then
brick back up to the wall and move on so the wall wouldn't
fall in on itself," Melancon said. "We could run
the electrical but we couldn't get the final power going."
Minnesota-based Carlson Group vowed to have the Country Inn
& Suites open in time for the soft opening in January,
said Bret Smith, vice president of hotel development services
for Carlson Hotels worldwide.
"This is the first time we have tried a historic adaptation
to the brand, which is generally one concept from one location
to another because they feature ground-up, new hotels,"
Smith said.
Carlson decided to build this flagship, concept hotel in
New Orleans primarily because of the historic tax credits
offered by the Historic District Landmark Commission, the
National Park Service and the state.
"The tax incentives were so attractive, we couldn't
walk away from that," Smith said.
The New Orleans structures wrap around a central, open courtyard,
a unifying theme that also fits right into the local, French
Quarter ambience. There is a swimming pool in the courtyard
(a must for Country Inn & Suites), as well as a fitness
room and sundry shop.
Carlson boldly "took some risks" in allowing the
architect to create a French Quarter-type balcony setting
and an interior atrium, Campo said. By installing refurbished
monitors, a skylight and ornate wrought-iron work and removing
two-thirds of the joists in one particular section, the architect
created an open feel in an area with no exterior windows.
"That atrium became the marquee of that project,"
Campo said. "As soon as you enter the building, you automatically
pick up the historic fabric and texture of building."
Removing the 200-ft. rafters to create the atrium wasn't
easy.
"We had to take them out 25 ft. at a time to maintain
the structural integrity of the building," Melancon said.
"Campo is only a few blocks away, which worked out really
great. We needed that on a job like this, or carte blanche
to take care of whatever in the field."
|